Chapter 13 PowerPoint document
Download
Report
Transcript Chapter 13 PowerPoint document
Chapter 13 Irreversibility risk and uncertainty
13.1 Individual decision making in the face of risk
13.2 Option price and option value
13.3 Risk and irreversibility
13.4 Environmental cost-benefit analysis revisited
13.5 Decision theory: choices under uncertainty
13.6 A safe minimum standard of conservation
In this chapter
you will learn about the difference between risk and uncertainty
find out how risk affects environmental decision making and have the concepts of
option value and option price explained
see how irreversibility affects environmental decision making and learn about
quasi-option value
consider decision making in the face of uncertainty
be introduced to the safe minimum standard and the precautionary principle
learn how environmental performance bonds could work
Risk and uncertainty
Risk – where all possible consequences of a decision can be completely enumerated
and probabilities assigned to each possible ‘state of the world’, ‘state of nature’,
‘state’
Uncertainty – where where all possible consequences of a decision can be
enumerated, but probabilities cannot be assigned
Radical uncertainty - where all possible consequences of a decision cannot be
enumerated
Risk/uncertainty distinction not always made in economics
Lack of objective probabilities (gambling, insurance) sometimes dealt with by
assigning subjective probabilities
In many environmental contexts, probabilities are assigned on the basis of modelling
– urban air pollution, nuclear accidents
The climate change problem exemplifies radical uncertainty
The St Petersburg paradox
A fair coin will be tossed repeatedly until it lands tail up. If it falls head up at the first toss, the gambler
gets £1. If it falls head up at the second toss, the gambler gets £2, at the third toss £4, at the fourth £8, and so
on. Tossing continues until the coin falls tail up. How much would somebody be willing to pay for such a
gamble?
The answer might appear to be ‘an infinite amount’ because the expected monetary value of the gamble is
infinite. The expected value is the sum of the probability-weighted possible outcomes, which in this case is
the infinite series
(0.5 1) (0.52 2) (0.53 4) (0.54 8)
... 0.5 0.5 0.5 0.5 ...
which has an infinite sum. That anybody would be prepared to pay a very large amount of money for such
a gamble violates everyday experience, and the example is known as the Bernoulli, or St Petersburg, paradox.
The paradox can be resolved by assuming that individuals assess gambles in terms of expected utility,
rather than expected monetary value, and that the utility function exhibits diminishing marginal utility. The
relevant outcome is then the infinite series
0.5U (1) 0.52U (2) 0.53U (4) 0.54U (8) ...
which has a finite sum, so long as there is some upper limit to U, which is what diminishing marginal
utility implies.
In economics, the basic approach to the analysis of individual behaviour in any kind of risky situation is
to assume the maximisation of expected utility and diminishing marginal utility.
Basic concepts for risk analysis 1
Expected value
Expected utility
Risk neutrality, aversion, preference
Certainty equivalence
Cost of risk bearing
The expected value of gamble with income outcomes Y1 and Y2 probabilities p1 and p2 is
E[Y ] p1Y1 (1 p1 )Y2
(13.1)
The expected utility of the gamble is
E[U ] p1U (Y1 ) (1 p1 )U (Y2 )
(13.2)
The certainty equivalent of the gamble is the value for Y that solves
U (Y ) E[U ]
The cost of risk bearing is the difference between the expected value of the gamble and its
certainty equivalent
Basic concepts for risk analysis 2
For U = Ya, 0<a<1, expected utility is
E[U ] p1Y1a (1 p1 )Ya2
(13.3)
and the certainty equivalent is the solution for Y in
Ya p1Y1a (1 p1 )Y2a
(13.4)
Y** is the expected value of the gamble
Y* is the certainty equivalent of the gamble
For U=Ya, 0<a<1, Y* < Y**
This individual is risk averse and
CORB = Y** - Y*
(13.5)
For a = 1, get risk neutrality
For risk preference arc ADEB would lie below
straight line ACB, with ∂U/∂Y > 0 and
∂2U/∂Y2 > 0
Option price and option value 1
Consider an individual and a national park wilderness area.
A – available, the park is open
N – the park is closed
U(A) –utility for income YA, park open
and wants to visit
U(N) – utility for income YA, park closed
and wants to visit.
p1 – probability of N, 1-p1 of A
NCA as p1 varies
Y** is the expected value of the outcome
Y* is the certainty equivalent
Option price and option value 2
YA – Y** is the expected value of the
individual’s compensating surplus, E[CS].
YA – Y* is option price, OP, the maximum that
the individual would be willing to pay for an
option that guaranteed access to an open park.
For Figure 13.2 U function, risk aversion, Y**
> Y* has OP > E[CS].
OP = E[CS] + OV
(13.6)
with OV, option value, positive.
With risk neutrality, NCA and arc NA coincide
and OV would be zero.
Option value is a risk aversion premium
E[CS] understates the benefit of keeping the park open as risk averse
individuals would be willing to pay a premium to avoid risk
Option price and option value 3
Risk also attaches to whether the individual wants to visit
The weather determines whether or not the individual wants to visit on a
given weekend – fine wants to go, not otherwise.
With park open for free WTP for entry on a fine weekend is £10
Probability of fine weather 0.5
E[CS] = £5.
Individual told park might be closed next weekend, and offered ticket
guaranteeing access. With no risk aversion, ticket is worth E[CS], £5.
If the risk averse individual, in order to avoid risk of wanting to go but
not being able to get in, is WTP £6 then option price is £6 and option
value is £1.
Risk and irreversibility
For a risk averse individual, option price exceeds expected compensating surplus by
option value.
If social decision making adopts consumer sovereignty, given observed actual risk
aversion, option price should be used in ECBA.
With respect to wilderness development this implies that the level of net development
benefits required to justify development needs to be greater than in a world where the
future is certain.
There are arguments that work in the same direction – require larger net development
benefits to justify development – that do not require the risk aversion assumption.
These use imperfect knowledge of the future and irreversibility.
Wilderness development ( also nuclear power ) can reasonably be regarded as
irreversible, given the timescales typically involved in any regeneration.
The decision not to develop is reversible.
Identification of maximum net benefit
A is flow of wilderness services,
decreasing with extent of
development.
Costs and benefits are functions of
A
A* - wilderness service flow that
corresponds to allocative efficiency
A* can be represented as
MC(A) = MB(A)
Maximum NB(A)
MNB(A) = 0
Irreversibility – future known
1 is now. 2 is the future
Future net benefits in present value terms
Following Krutilla-Fisher arguments, future
MNB2 higher than MNB1 for given A
Without irreversibility get A2NI > A1NI
With irreversibility A2 cannot be larger than A1
Myopia would mean A1NI and A’2
It means period 1 gain abc, period 2 loss
edhi.
Taking account of irreversibility would
mean A1I and A2I – ab = de.
Cost of irreversibility in period 1 is abc
Cost of irreversibility in period 2 is def
Irreversibility in a risky world
At start of period 1 can assign probabilities p to
MNB21 and q = (1 – p) to MNB22.
Working with the expected value for period 2
leads to A1IR and A2IR
Adding risk to irreversibility leads to lower A –
more development – than irreversibility alone
But, to less development than if irreversibility
were ignored.
Quasi-option value 1
Where there is the prospect of improved information ‘the expected benefits of an irreversible
decision should be adjusted to reflect the loss of options that it entails’ Arrow and Fisher
Even if the decision maker is risk-neutral
The size of the adjustment is quasi-option value
All or nothing development to simplify.
Decision to be taken at start of period 1 when period 1 conditions fully known and period 2
outcomes listed and probabilities attached. At the end of period 1, complete knowledge about
period 2 will become available
The decision at the start of period 1 is whether to permit development
Table 13.1 Two – period development/preservation options
Option
Period 1
Period 2
Return
1
D
D
R1 = (Bd1 – Cd1) + Bd2
D – development
P – preservation
Ri – return to option i
Bpt – preservation benefits
2
P
D
R2 = Bp1 + (Bd2 – Cd2)
3
P
P
R3 = Bp1 + Bp2
Bdt – development
benefits
Cdt – development costs
4
D
P
Is infeasible
period 2 costs and benefits
as present values
Quasi-option value 2
The return to proceeding immediately with development is
R d R1 ( Bd 1 Cd 1 ) Bd 2
(13.20)
The return to the decision to preserve at the start of period 1 is
R p Bp1 max{Bp 2 ,( Bd 2 Cd 2 )}
(13.21)
Suppose for moment that decision maker had complete knowledge at start of period 1.
Decision would be to develop if Rd>Rp, Rd – Rp>0, which from 13.20 and 13.21 is
( Bd 1 Cd 1 ) Bd 2 Bp1 max{Bp 2 ,( Bd 2 Cd 2 )} 0
(13.22)
which can be written
N1 Bd 2 max{B p 2 , ( Bd 2 Cd 2 )} 0
(13.23)
with N1 = (Bd1 – Cd1) – Bp1, that which would actually be known at the start of period 1
The other terms in (13.23) could not be known at the start of period 1, so it is not an operational
decision rule.
But, by assumption the decision maker does at the start of period 1 know the possible outcomes for
Bd2, Bp2 and (Bd2 – Cd2) and can attach probabilities.
Question - ? use the rule develop at start of period 1 if
N1 E[ Bd 2 ] max{E[ Bp 2 ], E[( Bd 2 Cd 2 )]} 0
(13.24)
Quasi-option value 3
Answer – no, using this rule would ignore the fact that full information will become
available at the start of period 2. The decision maker does not have full information at
the start of period 1, but she does know the possibilities and probabilities.
The proper decision rule is go ahead with development at the start of period 1 if
N1 E[ Bd 2 ] E[max{B p 2 , ( Bd 2 Cd 2 )}] 0
(13.25)
Whereas in 13.24 the decision maker uses the maximum of of the expected values
of period 2 preservation and development benefits, in 13.25 she uses the
expectation of the maximum of period 2 preservation benefits and net development
benefits.
The left hand side of 13.25 will be larger than the left hand side of 13.24, so the
former, ie 13.25, is a harder test to pass at the start of period 1.
The difference between the left hand sides of 13.25 and 13.24 is quasi-option
value.
Quasi-option value is the amount by which a net benefit assessment which simply
replaces outcomes by their expectations should be reduced, given irreversibility, to
reflect the pay-off to keeping options open by not developing until more
information about future conditions is available.
Quasi-option value – a numerical example
Two possible period 2 situations, A and B, are differentiated only by what preservation benefits
in the future will turnout to be.
For A and B, (Bd2 – Cd2) = 6
For A Bp2 = 10, for B Bp2 = 5
pA = pB = 0.5
Then, for 13.24 the third term on the lhs is.
max{E[ Bp2 ], E[( Bd2 Cd2 )]} max{[(0.5 10)
(0.5 5)],[(0.5 6) (0.5 6)]}
max{7.5,6} 7.5
A where Bp2 ( Bd2 Cd2 ), Bp2 10, p A 0.5
B where Bp2 ( Bd2 Cd2 ),( Bd2 Cd2 ) 6, p B 0.5
Hence
so the development gets the go-ahead if
N1 E[ Bd2 ] 7.5 0
For 13.25 we have two possible outcomes
(13.26)
E[max{Bp2 ,( Bd2 Cd2 )}] (0.5 10) (0.5 6)
8
and following this decision rule, the
development gets the go-ahead if
N1 E[ Bd2 ] 8 0
(13.27)
Suppose N1 + E[Bd2] = 7.75. Then, using 13.24/13.26 development would be decided on at the
start of period 1, while using 13.25/13.27 the decision would be to preserve in period 1. The test
based on 13.25 is harder to pass than the 13.24-based test.
The 13.25 test adds a premium to the 13.24 test – Quasi-option value which is 0.5 here.
Quasi-option value 4
Positive quasi-option value is a general result – Arrow and Fisher 1974
If, as in the numerical example
E[Bp2] > E[(Bd2 – Cd2)]
then 13.24 becomes
N1 E[ Bd2 ] E[ Bp2 ] 0
(13.28)
Now consider max{Bp2, (Bd2 – Cd2)} from 13.26, which is either Bp2 or
a larger number.So long as decision maker entertains the possibility that
(Bd2 – Cd2) > Bp2, E[max{Bp2, (Bd2 – Cd2)}] will be greater than E[Bp2]
and 13.25 which is
N1 E[ Bd 2 ] E[max{Bp2 , ( Bd 2 Cd 2 )}] 0
will be a harder test to pass than 13.28, with
E[max{Bp2 , ( Bd 2 Cd 2 )}] E[ Bp2 ] QOV
where QOV stands for Quasi-option value
Environmental cost-benefit analysis revisited 1
How should ECBA take account of risk? For risk neutrality instead of
T
T
NPV {B(D)t C (D)}e dt {B(P) t }e rt dt
rt
0
0
use
T
T
{E[ B(P)]t }e rt dt
E[NPV] {E[ B(D)]t E[C (D)]t }e rt dt
(13.29)
0
0
However, individuals are risk averse and if this is to be reflected in ECBA, it should use
T
T
T
0
0
NPV* {E[ B(D)]t E[C (D)]t }e rt dt {E[ B(P)]t }e rt dt CORBt e rt dt
0
(13.30)
for the test, where CORBt is the cost of risk bearing at time t.
It is sometimes suggested that risk can be dealt with Tby using expected values and an a higher discount rate:
T
NPV** {E[ B(D)]t E[C (D)]t }e ( r b )t dt
0
{E[ B (P)]t }e ( r b )tdt
(13.31)
0
where b is the ‘risk premium’. This implies that the cost of risk bearing is decreasing exponentially with time
T
T
bt
rt
NPV** {E[ B(D)]t E[C (D)]t }{CORBe }e dt {E[ B(P)]t }{CORBe }e dt
0
bt
rt
0
which is not generally the case. CORBt should be estimated over the project lifetime and used as in 13.30.
Environmental cost-benefit analysis revisited 2
Environmental services are typically public goods, so that the risk spreading argument cannot be
used to exclude consideration of CORBt. ECBA that does not ignore risk should use either13.30 with
E[B(P)]t replaced by E[CS]t and CORBt replaced by OVt, that is
T
NPV* {E[ B(D)]t E[C (D)]t }e rt dt
0
T
T
{E[CS]t }e dt OVt e rt dt
rt
0
(13.32)
0
or replace both E[B(P)]t and CORBt with OPt and use
T
NPV* {E[ B(D)]t E[C (D)]t }e dt
0
rt
T
OPt e rt dt
0
(13.33)
where CS is compensating surplus, OV is option value, and OP is option price.
Putting numbers to option values and quasi-option values is difficult. Often judgemental
allowance is made and sensitivity analysis conducted.
Decision theory: choices under uncertainty 1
A game against nature
Table 13.2 A pay-off matrix
C
Two strategies
D
E
A - Preservation
B - Development
A Conserve the
wilderness area as a
national park
B Allow the mine to be
developed
120
50
10
Three states of nature
C – High Preservation Benefit
5
30
140
Low return to mine
D – Intermediate Preservation and
development
E – Low Preservation Benefit
High return to development
Decision theory: choices under uncertainty 2
Table 13.2 A pay-off matrix
A Conserve
the wilderness
area as a
national park
B Allow the
mine to be
developed
C
D
E
bad worst outcome – is A
120
50
10
Maximax – select the best of the best
outcomes – is B
5
30
140
Table 13.3 A regret matrix
C
Maximin - select the strategy with the least-
D
E
Minimax regret – form the regret matrix
with entries that are the difference between the
actual pay-off and what it would have been
under the best strategy for the given state of
nature – minimax on regret by selecting for the
lowest of the largest regret - outcome is B
Subjective probability assignment –
A
0
0
130
B
115
20
0
on basis of principle of insufficient reason assign
equal probabilities to each outcome and select
for largest expected value pay-off – outcome is
A for 60 (B is 58.33)
A safe minimum standard of conservation
Table 13.4 A regret matrix for the
possibility of species extinction
F
U
A
130
0
B
0
z
Radical uncertainty – cannot list all possible outcomes
If mine goes ahead, possibly unique, plant population will
be destroyed. Project includes attempted re-establishment
of plant population at new location. With no previous
experience. No way of assigning probability of success to
possible prevention of species extinction.
F – state of nature favourable, relocation successful
U – state of nature unfavourable, relocation
unsuccessful
A - do not develop
z is an unknown number.
B – develop
Safe minimum standard - use minimax regret assuming z large enough to make A the right
strategy. Because species extinction involves an irreversible reduction in the stock of potentially useful
resources, of unknown future value. There are two kinds of ignorance
Regarding future preferences, needs and technologies
About the characteristics of existing species as they relate to future circumstances
Presume z is large enough to make A – do not develop – the correct strategy with minimax regret
A modified safe minimum standard
SMS is a very conservative rule. Any project that entailed the possibility of species extinction
would get stopped. However large, current gains would be foregone for possible avoided future
costs, presumed larger.
A modified SMS would adopt the strategy that ensures survival of the species provided that it
does not entail socially unacceptably large current costs.
How to determine what is currently ‘socially unacceptable’?
A modified SMS can be applied to target setting for pollution policy – set standards according
to efficiency criteria subject to SMS constraints – accord efficiency a lower priority than
conservation except where the two conflict, provided that the opportunity costs of conservation
are not excessive.
Box 13.1 Stern climate change review 1
Economic activity
Emissions
Sinks
Concentrations
A schematic representation of the
structure of the enhanced
greenhouse effect.
Dotted lines represent feedback
effects. Examples – methane
release, weakened carbon sinks.
Our knowledge of all of the links is
highly imperfect.
Climate
Biosphere
Humans
Figure 13.6 The enhanced greenhouse effect
The climate change problem is
characterised by uncertainty
Box 13.1 Stern climate change review 2
The 1992 United Nations Framework Convention on Climate Change adopted a Safe Minimum Standard
approach to the problem. Article 2, Objectives, states that:
The ultimate objective of this Convention and any related legal
instruments that the Conference of the Parties may adopt is to
achieve, in accordance with the relevant provisions of the
Convention, stabilization of greenhouse gas concentrations in the
atmosphere at a level that would prevent dangerous anthropogenic
interference with the climate system.
This is actually a modified SMS in that Article 2 goes on to say that this is subject to enabling 'economic
development to proceed in a sustainable manner'.
The role of uncertainty is explicitly recognised in Article 3, Principles, where it is stated that
3. The Parties should take precautionary measures to anticipate,
prevent or minimize the causes of climate change and mitigate its
adverse effects. Where there are threats of serious or irreversible
damage, lack of full scientific certainty should not be used as a
reason for postponing such measures, .........
The EU also adopts a precautionary approach, and it has operationalised it as meaning that the change in
global average temperature should not be more than 2oC above the pre-industrial level. A number of NGOs
have endorsed this objective. (It was endorsed at the Copenhagen UNFCC COP December 2009)
Box 13.1 Stern climate change review 3
The review notes the distinction between risk and uncertainty, and that the fact of
the latter suggests a precautionary approach to decision making, which is different
from risk aversion.
In its formal analysis of the costs of climate change the review actually uses the
standard expected utility framework with risk aversion. An integrated assessment
model, IAM, projects global GDP under business as usual with and without the
effects of climate change. The difference gives a trajectory of GDP loss on account
of climate change, which is converted to utility and expressed in BGE loss terms as
per Box 3.1 here.
For each climatic parameter, Stern constructed a subjective probability distribution.
For a given scenario IAM run 1000 times with climatic parameters drawn
randomly from their distributions. So, for each scenario get 1000 BGE losses,
reported as means across 1000 runs together with 5th and 95th percentiles.
Box 13.1 Stern climate change review 4
Table 13.4 Losses on BAU across six scenarios
Scenario
BGE equivalents: % loss in current consumption
Climate
Economic
Baseline
Climate
High
Climate
5th percentile
Mean
95th percentile
Market impacts
0.3
2.1
5.9
Market impacts
+ risk of
catastrophes
0.6
5.0
12.3
Market impacts
+ risk of
catastrophes
+ non-market
impacts
2.2
10.9
27.4
Market impacts
0.3
2.5
7.5
Market impacts
+ risk of
catastrophes
0.9
6.9
16.5
Market impacts
+ risk of
catastrophes
+ non-market
impacts
2.7
14.4
32.6
High climate IAM includes
feedbacks from methane release
and weakened carbon sinks as
temperature increases.
Utility discount rate 0.01
Elasticity of marginal utility of
consumption 1
Box 13.1 Stern climate change review 5
Mitigation costs
Bottom-up: 1% of of GDP (range –1 to 3.5%) for cutting to 75% of current
level by 2050 – consistent with stabilisation at 550 ppm CO2e.
Top-down: 1% of GDP (+/- 3%) for an emissions trajectory leading to
stabilisation around 500-550 ppm CO2e.
Target setting in terms of concentrations.
Stern does not try to optimise. Looks ( chapter 13) at dis-aggregated impacts and costs,
and supports with IAM scenario results.
‘the stabilisation goal should lie within the range 450-500 ppm CO2e’
‘550 ppm CO2e would be a dangerous place to be, with substantial risks of very
unpleasant outcome’
aiming below 450 CO2e ‘would impose very high adjustment costs in the near term for
relatively small gains, and might not even be feasible’
Stern argument is based a modified safe minimum standard – a target of 550 ppm CO2e
is affordable and would avoid the worst that can be envisaged. A target of 450 ppm
CO2e would be safer, but would cost a lot more, and may already be infeasible.
The precautionary principle
The precautionary principle is closely related to the modified safe minimum standard and is
gaining widespread acceptance, at the governmental and intergovernmental levels, as a concept
that should inform environmental policy. Statements of the precautionary principle have been
made by a number of governments, by individuals, and as part of inter-national agreements. Thus,
for example, Principle 15 of the June 1992 Rio Declaration is that:
In order to protect the environment, the precautionary approach shall be widely applied by States
according to their capabilities. Where there are threats of serious or irreversible damage, lack of full scientific
certainty shall not be used as a reason for postponing cost-effective measures to prevent environmental
degradation.
Like the SMS, the precautionary principle can be taken as saying that there is a presumption
against going ahead with projects that have serious irreversible environmental consequences,
unless it can be shown that not to go ahead would involve unacceptable costs. The question
which arises is whether there are any policy instruments that are consistent with this approach to
irreversibility and uncertainty, which could constitute a feasible means for its implementation in
such a way as to avoid an outcome that simply prohibits such projects.
Environmental performance bonds 1
Environmental performance bonds have been suggested as a response to the problem of devising a means
of project appraisal which takes on board the ideas behind the SMS and the precautionary principle.
Some firm which wishes to undertake a project involving major technological innovation, so that there is
no past experience according to which probabilities can be assigned to all possible outcomes. In so far as
genuine novelty is involved, there is radical uncertainty in that not all of the possible outcomes can be
anticipated. An example of such a project would have been the construction of the first nuclear power plant.
Assume an environmental protection agency (EPA) without permission from which the firm cannot go
ahead with the project. The EPA takes independent expert advice on the project, and comes to a view about
the worst conceivable environmental outcome of the project’s going ahead. Approval of the project is then
conditional on the firm depositing with the EPA (‘posting’) a bond of $x, where this is the estimate of the
social cost of the worst conceivable outcome.
The bond is fully or partially returned to the firm at the end of the project’s lifetime (defined by the
longest-lasting conceived consequence of the project, not by the date at which it ceases to produce output)
according to the damage actually occurring over the lifetime.
If there is no damage the firm gets back $x, plus some proportion of the interest. The withheld proportion
of the interest is to cover EPA administration costs and to finance EPA research.
If the damage actually occurring is $y, the firm gets back $x – $y, with appropriate interest adjustment.
For $x equal to or greater than $y, the firm gets nothing back, forfeiting the full value of the bond.
Environmental performance bonds 2
The advantages claimed for such an instrument are in terms of the incentives it creates for the firm to
undertake research to investigate environmental impact and means to reduce it, as well as in terms of
stopping projects.
Suppose that the EPA decides on $x as the size of the bond, and that the firm assesses lifetime project net
returns to it as $(x – 1), and accepts that $x is the appropriate estimate of actual damage to arise. Then it will
not wish to go ahead with the project. If, however, the firm took the view that actual damage would be $(x –
2) or less, it would wish to go ahead with the project. The firm has, then, an incentive to itself assess the
damage that the project could cause, and to research means to reduce that damage.
If it does undertake the project it has an ongoing incentive to seek damage-minimising methods of
operation, so as to increase the eventual size of the sum returned to it, $x – $y.
At the end of the project’s lifetime, the burden of proof as to the magnitude of actual damage would rest
with the firm. The presumption would be that the bond was not returnable. It would be up to the firm to
convince the EPA that actual damage was less than $x if it wished to get any of its money back. This would
generate incentives for the firm to monitor damage in convincing ways, as well as to research means to
minimise damage.
In the event that damage up to the amount of the bond, $x, occurred, society would have received
compensation. If damage in excess of $x had occurred, society would not receive full compensation.
$x is to be set at the largest amount of damage seen as conceivable by the EPA at the outset. A socially
responsible EPA would take a cautious view of the available evidence, implying a high figure for $x, so that
society would not find itself uncompensated.