Activity Summary & Status
November 28, 2000
NANC Toll-Free IMG
Activity Summary & Status
• Activities Since the October Meeting
– 10/23/00 Virtual Meeting- 21 Participants
• Agreed to move forward w/ Technical
Requirement Document, cease work on FSD
– 10/10/00 Virtual Meeting- 18 Participants
• No Consensus Regarding competitive bid
• Reviewed contributions in preparation for
Dallas face-to-face meeting
NANC Toll-Free IMG
Activity Summary & Status
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Number Company
Contribution Title
Date Submitted
1
WorldCom Management and Oversight of Toll Free Administration
10/10/00
2
QWEST Revised text for Contribution: Security & Data Maintenance10/24/00
3
Richard BartelFCC Part 52 Regulations on Warehousing and Hoarding10/27/00
4
ATT
Reports
10/27/00
5
Verizon
SMS Transaction Rate 10/31/00
6
Sprint
NIIF Draft Document 11/1/00
7
Sprint/SBC TF IMG Guidelines for Technical Requirements Document 11/2/00
8
WorldCom Response to Bell South Questions 11/2/00
9
DMSI
Response to SMS Transaction Rate
11/2/00
10
Bell South Work Plan and Load Management 11/6/00
11
Verizon
Section 9.0 11/6/00
12
WorldCom Competitive Bid
11/10/00
13
Sprint
Text
11/13/00
14
WorldCom System Flexibility
11/14/00
15
Judith Oppenheimer Text for Section 1.5
11/14/00
NANC Toll-Free IMG
Activity Summary & Status
• Activities since the October Meeting
– November 14 through 16, 2000, face-toface meeting
• Baseline text agreed to for sections 1-4 of the
technical requirement document
• Agreement reached to request more time (3
months) to complete work
NANC Toll-Free IMG
Activity Summary & Status
•
•
•
•
* Toll-Free/LNP Comparison
Toll-Free 31.68 Million Numbers
LNP 10.847 Million Numbers Ported
Toll-Free Record size up 255 K Bytes
LNP Record size 500 Bytes
NANC Toll-Free IMG
Activity Summary & Status
•
Technical Requirement Document
•
Table of Contents
•
•
•
•
•
•
•
•
•
•
•
•
Section
1.0
Introduction
2.0
RespOrg Interface
3.0
Features/Functionality/Record Maintenance
4.0
Routing Network Interface
5.0
System Characteristics and Performance
6.0
Operations/Administration/Maintenance
7.0
RespOrg Changes
8.0
Structure
9.0
Oversight/Compliance
10.0
Quantification
11.0
Acronyms and Definitions
•
•
•
Appendices
A
Requirements Trace-ability Matrix
B
Standard Reports
NANC Toll-Free IMG
Activity Summary & Status
• Planned Activities
– 12/4/00, Conference Call to review
contributions (due 11/29/00)
– 12/6-8/00, Meeting, Toronto
– 12/22/00 Conference Call
– 1/9-11/01, Meeting, San Francisco
– 1/30 through 2/1/01, Meeting, Atlanta
– 2/13-15/01, Meeting, Location TBD