CRYOGENIC TEST STATIONS FOR FReSCa2
Download
Report
Transcript CRYOGENIC TEST STATIONS FOR FReSCa2
Plan for test station
Marta Bajko
For the Technical Review of FReSCa2
June 2015 Saclay Paris
CRYOGENIC TEST STATIONS FOR
LN2 for mechanical structure
•
•
•
Cryogenics
• Cooling lines
• Control
Cryostat
• LN2 vessel
• Insert for magnet support
Measuring systems
• Strain and Temperature
A non exhaustive list of ingredients….
LHe for cold powering test
•
Cryogenic system
–
–
–
–
•
Cryostat
–
–
•
He vessel
Insert for magnet support and communication
with outside
Electrical circuit
–
–
–
–
–
–
•
LHe lines
Pumping system
He gas recovery
Control ( Soft and Hard)
Power converter
Water cooled cables
Commutator, Switch, Dump Resistor
Connection to Current Leads at RT
Current Leads
Connection to magnet
Measuring systems
–
–
–
Quench detection,
Magnet protection
DAQ, magnetic measurements, RRR, Splice
resistance, AC losses,
Cryogenic test facility for
in SM18. Layout.
Installation for LHe power test
Vertical test benches
Horizontal test benches
Vertical test installations for 77 K
Installation for LN2 test
19/09/2012
Marta Bajko TE-MSC TF
3
Holding structure
and scaffolding
test station layout SM18
Magnet Flushing Station
recuperated from LHC Main
Magnet series tests activity
H. Bajas, M. Charrondiere, P. Viret, J.C. Perez
Transfer lines
recuperated
from CRG
Three thermal cycles RT 77K
LN2 tank
Cryostat
borrowed
from RF
Control Room
Temporary placed in
the parking area
100 K gradient constrain respected by automatic
Marta Bajko TE-MSC TF
regulated control
4
test station layout in SM18
C. Giloux, V. Benda, G.J Coelingh, H. Thiesen, C. Gonzalves Perez, P. Perret
General overview
Electrical circuit
for LHe test station
C. Giloux, V. Benda, A. John Lee, P. Perret
•
•
•
•
Cryogenic valves: are at CERN and ready to by sent to Criotec including instrumentation
Cryogenic distribution system : Preliminary design is done by Criotec
Quench buffer: preliminary design was not done yet by Cryother
Cryo control:
Phase separator
Quench line
Distribution valve box
control
D. De Paola, C. Fluder, M. Pezzetti, E. Asensi Conejero, C. Giloux, V. Benda
A. Vande Craen, V. Maire
• Vacuum tank delivered
• Helium vessel fabrication on-going
– Geometrical non-conformity discovered after
welding of the neck
• Wall alignment out of tolerance according to
pressure equipment standards
– Solution studied to find the best way to fix it
– Reparation will start this week
– Vessel has to be pressure and leak tested after
reparation
– Delivery at CERN expected week 28-29
A. Vande Craen, V. Maire
• Thermal shield fabrication on-going
– Wall formed
– Tube brazing started
– Delivery expected week 27
• MLI
– Order passed in March
– First version of drawings received for approval
– Delivery expected week 28
•
•
•
•
•
Parallel advancement for HFM (2x20kA + 2x15kA)
and Cluster D leads (2x30kA + 2x15kA)
3D design of all leads is terminated (fully resistive
type)
Functional specifications (operating parameters,
instrumentation) and specifications of interfaces
will be provided in two weeks
Execution drawings on-going (sub-components,
assembly procedures)
Procurement of raw materials and sub-components
on-going
Discussions ongoing with main workshop to assess
welding procedures for HEXs
ø250
ø132
ø166
ø190
ø166
ø132
No show-stoppers or significant delays expected at the
moment w.r.t. the planning provided
1655
•
440
A. Ballarino, S. Giannelli, R. Betemps
M. Strychalski , V. Maire, P. Viret, J.C. Perez
Current leads 15 kA
Connector boxes
For April 2016
Current leads 20 kA
Time
Design
Preparation
Fabrication +
assembly
Controls
Total
FReSCa2 magnet integration
on the insert
+ 3 months from now (Aug 2015)
2 months (Oct 2015)
~ 6 months (Apr 2016)
1 months (May 2016)
11 months
Actuator valve
design
V. Maire, C. Giloux., P. Viret
Material: Antico EN AW 6082 T6
In 4 parts
Thickness: 2 mm
Overall diameter : Ø 1596 mm
Weigth : 12 Kg
5x 90 mm
2x 200 mm
800 mm
Collars in bronze
( Di 50.25, De 90 mm, ep. 20 mm)
current leads and magnet
V. Maire, P. Minginette, P. Viret, J.C. Perez
476
mm
Connection between
magnet and current
leads at the level of
the current leads.
Magnet bus bars are
passing through the
lambda plate.
Max. Deformation: 5 mm
Max. Stress: < 40 MPa
1600
mm
Fresca 2
(9 Tonnes)
Cable clamped
with indium
44
13
Plaque lambda
Magnet
P. Perret, M. Strychalski, P. Viret, R. Rinaldesi
Lifting capacity : 25 t
Operating altitude of the crane : 6 m
Minimum length of the crane’s rope: 9. 3m
C. Giloux., E. Vergara, E. Page