Summary of Fuse Testing for Barrel Module Fuse Boxes
Download
Report
Transcript Summary of Fuse Testing for Barrel Module Fuse Boxes
Summary of Fuse Testing for
Barrel Module Fuse Boxes
Duke University
Jack Fowler
Fuse Box Production Summary
• Fuse Boxes have been in production for ~ 12
months
• 35 sets of each type are being produced
• This involves > 7500 fuses
• Fuses were delivered from Oct 03 until Aug 04
Fuse Box Production Steps
•
•
•
•
•
•
•
Assemble Fuse Box components and solder
Test Fuse Resistance
Clean Fuse boxes and dry
Test Fuse Resistance
Dry fuse boxes for minimum 3 hrs at < 55° C
Conformal coat fuse box components
Final Test Boxes - continuity at < 100 V and check
for breakdown at 2 kV
• Final assembly – add hardware and heat shrink and
label cables
Fuse Boxes
Post Production Tests
• Once fuse boxes are through the final test, we
perform simple resistance test on each of the
fuses.
• In the period of time between tests, the fuse
boxes are stored on a shelf in the lab.
Failed Resistance Test Post Production
Fuse Recovery
• The recovery was performed by applying ~ 600 V through a
6 MΩ resistor to all of the fuses. This applied ~ 100 µA
current. This was applied for 1 minute.
• The fuse resistance was tested and the results recorded.
Fuse Recovery
Fuse Conditioning after Recovery
• After recovery, all of the fuse boxes were connected in parallel
and a 100 µA current was applied.
• The fuse boxes were left in this condition.
• After 2 weeks, half of the boxes were removed and the fuse
resistance was tested. This included ~3500 fuses.
Fuse Box Conditioning
Fuse Box Connections
Fuse Tests after Two weeks of Conditioning
Summary
• Before recovery and conditioning, fuse failures seemed to be
stabilizing at ~ 0.1 % per week.
• Recovery was successful for 60 % of previously failed fuses.
• After 2 weeks of conditioning, 33 % of “recovered” fuses
failed.
• During 2 weeks of conditioning, an additional 8 fuses failed.
This equates to ~ 0.1%/week.
• An additional 3 of the “recovered” fuses failed 1 week later
bringing the failure rate to 40 %. No new fuses failed.
Future Plans
• Continue conditioning for the remaining half of the fuse boxes
for 2 more weeks.
• Continue testing post conditioned fuses weekly for additional
failures.
• Continue new design of fuse box without fuses. Resistors will
take the place of the fuses.