On detector electronics:
High voltage part
Tilecal session in ATLAS upgrade week (Tuesday 10 November 2009)
François Vazeille
What are the constraints for
the Dividers and the HV regulation?
Proposed R&D scheme
Status at Clermont-Ferrand
1
What are the constraints for
the Dividers and the HV regulation?
HV Dividers (see the specifications in my previous talks)
- To fit the space inside the PMT Blocks,
as interface in between the PMT and the 3in1 card without any cable.
- To keep the PMT linearity in the extreme sLHC luminosity, within 1%.
HV regulation (see the specifications in my previous talks)
- To reach at least the 0.5 V rms regulation stability, as specified by Tilecal.
- To be better by reaching the present ATLAS performances
at least 10 times better.
- To improve the present reliability and to bring new facilities
(Individual switching, access…)
knowing that the radiations will be bigger by about a factor 10 in the pit.
In any case, the cost and the funding will drive the final solution.
2
Proposed R&D scheme
DIVIDERS
New design using transistors in the last stages.
2009
0.5 FTE (0.25 Ie, 0.15 Tm, 0.1 on-line)
Comparison tests of old/new designs using the PMT Test Bench,
by putting DC currents simulating the MB induced events at sLHC.
Rebuilding of the Divider Test Bench.
2010
Choice of active components with respect to the expected radiation,
and radiation tests of new Dividers.
0.6 FTE (0.3 Ie, 0.1 Tm, 0.2 on-line)
Final scheme fitting the final 3in1 new design.
Depending from
the 3in1 schedule
Man power not yet estimated
but not big.
3
HV REGULATION
- 6 solutions + ASIC Options *
- Manpower if chosen
On Drawers
USA15
Option 0: Full re-use
- Aging: at least 15 years old in 2019.
- Radiations? True radiation level waited.
- Compatibility with new Drawers.
- No R&D manpower, except maintenance.
Option 3: Re-use of present cards
- Aging: at least 15 years old in 2019.
- Integration in USA Racks: space?
- Long cables for services + Drawer Bus.
- R&D manpower : 2.0 FTE (0.5Ie, 0.5Te,
0.5Tm + 0.5 on-line)
Option 1*: New design with COTs
- New radiation tests.
- New design.
- R&D manpower: 4.0 FTE (2Ie, 1Te + 0.5
Test Benches + 0.5 on-line)
Option 4*: New design
- Conception and integration in USA15,
including HV source (commercial?).
- Long cables for services + Drawer Bus.
- R&D manpower : 3.5 FTE (1.5Ie, 0.5Te,
0.5Tm, + 0.5 Test Benches + 0.5 on-line)
Option 2*: New design with radhard
components
… COST!
- Radiation tests to validate.
- New design
- R&D manpower : 4.0 FTE (2Ie, 1Te + 0.5
Test Benches + 0.5 on-line)
Option 5: Commercial solution (CAEN?)
… COST!
- Integration and long cables for
services + Drawer Bus.
- R&D manpower : 1.5 FTE (0.5Ie and Te,
0.5Tm + 0.5 on-line)
4
Schedule:
• In 2010:
- Comparison of the 6 (or 9) solutions, including the costs.
R&D manpower: 1 Ie.
- Propositions and final choice,
knowing that the funding will play an important role.
• In 2011-2012: Final design, with new Test Benches and other tests
See the previous table for the requested manpower.
5
Status at Clermont-Ferrand
DIVIDERS
At this moment: fits the foreseen schedule,
with manpower in 2009-10 and funding in 2009 (10 K€).
• New design
- Made (Michel Crouau).
- Order of components for 20 Dividers.
Delivery end January 2010.
- Lab tests on some Dividers
First validation.
Design and validation of new Divider Test Bench (Not before February).
- Systematic tests on the new Divider Test Bench, then on the PMT Test Bench.
using 20 PMT/Divider sets, before July.
• Divider Test bench (from the previous Test Bench)
- Mechanics: OK (Pierre Verdier).
- Electronics and commands: OK new Labview version (Roméo Bonnefoy),
except new test about DC current injection in transistors: in progress.
- On-line: in progress, Roméo then Patrick Lafarguette.
• Radiation tests to organize and to prepare in 2010,
with an active Test Bench during the radiation exposure.
6
HV REGULATION
The Clermont-Fd team is officially authorized (by LPC management) to work on
the comparison in 2010, and to make preliminary tests when requested.
- Manpower as requested : 1 Engineer in electronics.
- Table of options: first studies in 2009 by Robert Chadelas,
including the first cost estimates (From 0.5 M€ to more than 3 M€).
- Activity going on in 2010,
including special tests (Regulation loop, long cables and noise…).
Once the final option will be chosen by Tilecal
New request for manpower to LPC management.
7