Road Infrastructure Agency
Download
Report
Transcript Road Infrastructure Agency
Projects under Operational programme “Transport
and transport infrastructure” 2014-2020
Eng. Lazar Lazarov
Chairman of Road Infrastructure Agency Management board
28 - 29 November 2016
Sofia
“Kalotina – Sofia” MW Lot 1 Western Arc of Sofia Ring Road, Phase 2
Activity
Contractor
Contract Value VAT included
Construction
“European roads“ ASD
101 999 866,65 BGN
OVERPASS
BLVD. “LOMSKO SHOSE"
Motorway “Struma” Lot 3.1 from Blagoevgrad to Krupnik
from km 359+000 to km 366+000 and
from km 370+460 to km 376+000
Activity
Design and
Construction
Supervision
Contractor
„АМ Струма 3.1“ ASD
„SN АМ „Струма Лот
3.1“ ASD
Contract Value VAT
excluded
154 999 999,92 BGN
1 695 249,00 BGN
Motorway “Struma” Lot 3.1 - “Jeleznitsa” tunnel
Procedures are carried out under the PPA with the subject:
- Design and construction of the motorway "Struma“ Lot 3.1 Jeleznitsa
tunnel
- Supervision of the design and construction of the motorway "Struma"
Lot 3.1 Jeleznitsa tunnel
Motorway “Struma” Lot 3.3 from Kresna to Sandanski
from km 397 +000 to km 420 + 624 = 420 + 628 478 km
Overall length: 23.6 km
Activity
Contractor
Design and
Construction
Consortium “Struma” - Lot 3.3
Supervision
"Patinvest-engineering" JSC
Contract Value VAT
excluded
234 123 012,00 BGN
2 998 161,28 BGN
Motorway “Struma” Lot 3.3
An archaeological site 16 km 419 + 670 to km 420 + 384
village Damyanitsa, municipality of Sandanski, Blagoevgrad
Finds of the preliminary exploring
archaeological site 16 km 419 + 670 to km 420 + 384
VI – V century BC
III-IV century
Application Form for Struma Motorway Project – Lot 3.1, Lot 3.3
and Zheleznitsa Tunnel
• Received comments and remarks from Jaspers - May 2016
• Agreed with Jaspers updated traffic model and CBA
• Submission for Jaspers’ review of the updated Application form
and supporting documents – 19 December 2016
Struma Motorway Lot 3.2 from Krupnik to Kresna
• Lot 3.2 falls in the environmentally sensitive and technically
difficult construction area
• The intensive traffic on the road through the Kresna Gorge
increases the risk of traffic accidents involving casualties.
For Struma Motorway Lot 3.2 passage through the Kresna Gorge
various technical alternatives were developed.
Four alternatives (objects of the new EIA) had been currently
prepared:
• 15.4 km long tunnel (2008-2014)
• Dual Carriageway (2014)
• Dual Carriageway (2015)
• Eastern Bypass (2016)
Long Tunnel Alternative (2008-2014)
Dual Carriageway Alternatives (2014-2015)
Eastern Bypass Alternative (2016)
•
2 lanes and with a total width of 10.5 m
•
The new carriageway bypasses the Kresna Gorge from the east and the other
carriageway uses the existing road E-79 (I-1). The existing road will be
rehabilitate and mitigating measures to limit the risk of mortality of wild
animals and fragmentation of their habitats will be implement
EIA Procedure
•
Developed updated Terms of Reference for the scope and content of the
environmental impact assessment (EIA) of the investment proposal "Improved layout of Lot 3.2 of Struma Motorway“ will be issued.
Consultations with the specialized administrations, stakeholders and
public were performed
•
The statements had been received and processed. The reference for
consultations is under preparation as the ToR for EIA have been precised
and supplemented
•
The submission of the ToR for the EIA for consultation with the competent
authorities (MoEW and Ministry of Health) will occur in December 2016
•
Expected preparation of the first draft of the EIA /AA Report - March 2017
•
Submission of the EIA/AA Report in the MoEW for assessment of their
quality
•
Public consultation on the EIA/AA Report after positive assessment of their
quality by the MoEW.
Preparation of project: Road I-1 (E-79) Vidin-Montana-Vratsa,
approximate length: 126 km
Activity
Contractor
Contract Value
VAT included
DESIGN
І-st section – VidinDimovo, from km 3+757 to
km 39+480
ІІ-nd section – DimovoBela-Ruzhintsi, from km
39+480 to km 61+750
„VIA PLAN–BURDA”
ASD
1 045 081,28 BGN
ІІІ-rd section – RuzhintsiMontana, from km 61+750
to km 102+060
ІV-th section – MontanaVratsa, from km 111+305
to km 140+008
"Inzhkonsultproekt"
Ltd.
1 092 986,16 BGN
Preparation of project: Road I-1 (E-79) Vidin-Montana-Vratsa,
approximate length: 126 km
Activity
Environmental Impact Assessment
Contractor
Contract Value VAT
included
"Dango Project Consult" Ltd.
60 372,00 BGN
Auditing road safety on phase preliminary project and technical project
І-st section – Vidin- Dimovo, from km
3+757 to km 39+480
ІІ-nd section – Dimovo-Bela-Ruzhintsi, from
km 39+480 to km 61+750
„Safe roads ” ASD
10 000,00 BGN
ІІІ-rd section – Ruzhintsi-Montana, from km
61+750 to km 102+060
ІV-th section – Montana-Vratsa, from km
111+305 to km 140+008
„Road safety ” ASD
14 400,00 BGN
Start of design activity – July 2013
Deadline for preparation of technical projects – July 2018