Transcript Presentation Fourth Steering Committee Meeting
Twinning project
ENEA – ENforcing Environmental Acquis
4th Steering Committee
César Seoánez
Skopje, 9th of February, 2016
OUTLINE
4th quarter assessment (12 October 2015 – 11 January 2016)
Quarterly Report 4
Programme for next 6 months (12 January – 11 July 2016)
Operative Side Letter 5
Outputs delivered to Steering Committee
Addendum 2
Twinning Project
ENEA – ENforcing Environmental Acquis
4th QUARTER:
Coordination
Meetings: multiple, within missions, with stakeholders, including Inspection Council
Main outputs & conclusions so far communicated and forwarded
E-inspection software team communicate with SEI
Coordination with TA project supporting local level & Twinning IED
Coordination with training programme of TA project
Coordination meeting organised by MoEPP sharing & review of relevant docs
Mutual participation in workshops of Twinning & TA in November & December
Info exchange continues
Twinning Project
ENEA – ENforcing Environmental Acquis
4th QUARTER:
Communication
Website: www.sei.gov.mk
SEI banner now visible in MoEPP’s website
First promotional video published online
Estimate of visibility materials to be prepared in following months
Twinning Project
ENEA – ENforcing Environmental Acquis
4th QUARTER: Progress vs. Work Plan
Twinning Project
ENEA – ENforcing Environmental Acquis
4th QUARTER: Progress vs. Work Plan
Good
Twinning Project
ENEA – ENforcing Environmental Acquis
4th QUARTER:
Activities
October (starting 12th )
Activity 1.2, mission 7: factsheets for industrial sectors
Activity 1.2, mission 5: check lists for some waste streams
RTA Training in Brussels, 15-16 October
Activity 1.2, mission 4: last mission for general inspection manual
Activity 1.3, mission 3: preparation of training materials
Steering Committe 3
Twinning Project
ENEA – ENforcing Environmental Acquis
4th QUARTER:
Activities
November
Activity 3.1, follow-up of mission 1: BPMS assessment & 1st recommendations
Activity 2.1, mission 4: workshop & 1st draft of Law for Inspection on Environment
Activity 2.1, mission 6: other supporting materials & training on planning (IRAM)
Activity 1.2, mission 10: 2nd mission to finalise IPPC/BAT guidelines
Draft Addendum 2 & meetings with Inspection Council
December
Activity 2.2, mission 5: 4 one-day workshops on inspection cycle
Activity 1.2, mission 8: 2nd mission to finalise factsheets for industrial sectors
Updates to Addendum 2 upon request of CFCD
Twinning Project
ENEA – ENforcing Environmental Acquis
4th QUARTER:
Activities
Main outputs
SEI - Twinning website
Inspection manual
Draft sector inspection checklists & factsheets (12 sectors)
Trainings on IRAM & Inspection Cycle
Workshop & draft Law for Inspection on Environment
Draft proposals for indicators to evaluate inspectorate & inspectors
SEI’s BPMS assessment & first proposals for next steps
Twinning Project
ENEA – ENforcing Environmental Acquis
4th QUARTER:
Activities
Other outputs
Translation of Spanish templates for multiannual insp. plan & annual programme
First promotional video in FIIAPP’s web
Addendum 2
Twinning Project
ENEA – ENforcing Environmental Acquis
4th QUARTER: Participation BC experts
140 BC participants in meetings held in missions
A lot of drafting (to continue until February 2016)
Twinning Project
ENEA – ENforcing Environmental Acquis
4th QUARTER:
Expenditures
As planned
Savings in flight tickets
In 4th quarter ~ 19 % of activities’ budget
Twinning Project
ENEA – ENforcing Environmental Acquis
QUARTERLY REPORT
Addendum 2: training needs urgent endorsement
Central planning & control of inspectors
new Law should come into force
Inspection Council should address Twinning docs sent,
to align to EU best practices
Overload in planning & reporting, evaluation of inspectors with financial penalties...
Inspection Council activity should get the attention of EC
Paragraph slightly reformulated
Twinning Project
ENEA – ENforcing Environmental Acquis
QUARTERLY REPORT
Managers in SEI, MoEPP, CFCD, DEU & SEA should
continue pushing for a change in Law for Insp. Supervision
Review & implement recommendations for improvement
2nd update: deleted recommendation about E-inspection project, as it was cancelled
Twinning Project
ENEA – ENforcing Environmental Acquis
PROGRAMME NEXT 6 MONTHS
January
Activity 1.2, start of mission 6: 2nd mission for check lists waste streams
Activity 2.1, start of mission 8: control & remediation of old polluted sites
Activity 1.2, mission 11: 1st mission leaflet operators & communication strategy
February
Activity 2.1, mission 7: other supporting documents
Steering Committee 4
Activity 3.1, mission 2: proposals for BPMS improvement
Activity 1.2, mission 12: 2nd mission to finalise leaflet operators & comm strategy
Twinning Project
ENEA – ENforcing Environmental Acquis
PROGRAMME NEXT 6 MONTHS TRAINING
April-May
April-May
March
June
March-May
July
Twinning Project
ENEA – ENforcing Environmental Acquis
PROGRAMME NEXT 6 MONTHS
March
Activity 1.3, mission 4: 2 two-days trainings on industrial processes (regions 1 & 2)
Activity 1.3, mission 5: 2 two-days trainings on industrial processes (regions 3 & 4)
Activity 1.3, mission 6: training based on inspection to pilot installation (region 1)
April
Activity 1.4, mission 3: study visit to The Netherlands
Activity 1.3, mission 7: 3 one-day trainings on comm. skills & team building
Activity 2.2, mission 6: training based on inspection to pilot installation (region 3)
Twinning Project
ENEA – ENforcing Environmental Acquis
PROGRAMME NEXT 6 MONTHS
April
Steering Committee 5: 22nd April
Activity 3.1, mission 3: training on use of IRAM software
May
Activity 1.3, mission 8: 3 one-day trainings on comm. skills & team building
Activity 2.2, mission 7: training based on inspection to pilot installation (region 2)
Activity 3.1, mission 4: further work on BPMS (to be defined in missions 3.1.2-3)
Updated project’s brochure
Twinning Project
ENEA – ENforcing Environmental Acquis
PROGRAMME NEXT 6 MONTHS
June
Activity 2.2, mission 7: training based on inspection to pilot installation (region 4)
Activity 2.1, mission 9: first training on sampling & monitoring
Activity 2.1, mission 10: second training on sampling & monitoring
July(until 11th)
Closure event
Twinning Project
ENEA – ENforcing Environmental Acquis
OPERATIVE SIDE LETTER 5
Side letter 10: expert for mission 2.1.7 + 2 flights for act. 1.2
Included Marc du Maine in act. 1.3
Explicit approval of OSL is very welcome
Twinning Project
ENEA – ENforcing Environmental Acquis
COMMENTS TO OUTPUTS DELIVERED TO ST.C.?
2.1.4 – Draft Law for Inspection on Environment
2.1.4 – Report related to the draft Law, and Table of Concordance
3.1.1 – BPMS assessment and first proposals for next steps
2.1.6 – Procedure & minutes template for small incident/accident
2.1.6 – IRAM’s users guide
1.2.10 – Guidance on BAT on storage of hazardous and non-hazardous waste
1.2.10 – Guidance on “mirror code waste” classification
1.2.6 & 1.2.8 – 12 sector & waste inspection checklists
2.1.8 – Issues to comply with EU legislation on soil protection
2.1.7 – Indicators to evaluate inspectors & Inspectorate
Twinning Project
ENEA – ENforcing Environmental Acquis
ADDENDUM 2
Need for urgent endorsement
Training missions in March RTA affected
Study tour in April participation of RTA Assistant and of 11th participant
All your support is needed!
Twinning Project
ENEA – ENforcing Environmental Acquis
Thank you very much !
Благодарам многу!