Transcript PPT - unece

Pre-application process in
England and Wales
Sixth meeting of the Task Force on
Public Participation in Decisionmaking under the Aarhus
Convention 10-11 February 2016

To outline basic features of Planning Act 2008 regime

To show role of pre-application process
Planning Act 2008

Primary mechanism in England and Wales for the
consenting of “nationally significant infrastructure
projects”. For instance, onshore generating stations
over 50MW.

Different to general town and country planning.

Secretary of State the decision maker following
recommendations from an inspector (or inspectors).
Time-limits and process
Stage of the Development
Consent Process
Pre-application
Acceptance
Pre-examination
Opportunity for Public Participation
Timescale
Before submitting an application, the developer is required to carry out extensive
public consultation on their proposals. Before consulting, the developer prepares a
Statement of Community Consultation setting out how they intend to consult on
their proposal. Information relating to the Hinkley Point C consultation was placed
on the developer’s public website.
No statutory duration (usually around 1-2
years)
The Planning Inspectorate decides whether or not the application meets the
required standards to proceed to examination – including whether the developer’s
pre-application consultation has been adequate.
28 days
All information on the case is available on the Planning Inspectorate website.
Anyone can register as an interested party (on the internet or by post). They will
then be kept informed of progress and opportunities to put their case. There will be
a preliminary meeting open to interested parties and a timetable of the examination
will be set.
No statutory duration (usually around 3-4
months)
Time-limits and process (2)
Examination
Recommendation
Decision
Post-Decision
All interested parties are invited to provide further written evidence. The
Examining Authority may ask interested parties questions to clarify their
evidence. All interested parties have the opportunity to comment on other
representations and respond to comments made about their representations.
Sometimes hearings may also be held on particular issues. The Planning
Inspectorate website is kept updated with new material throughout the
Examination period.
Up to 6 months
The Examining Authority prepares a report with its conclusions and
recommendation for the Secretary of State taking into account all representations it
has received.
Up to 3 months from the end of the
examination
The Secretary of State makes a decision whether or not to grant consent. This is
communicated to all parties, and all of the decision-making documents are placed
on the Planning Inspectorate website. In making this decision, the Secretary of
State takes into account representations received following the end of the
examination.
Up to 3 months from the receipt of the
Examining Authority’s report
Decisions may be challenged in the High Court.
Challenges must be issued with 6 weeks
of the decisions
Pre-application outcomes
Outcomes of effective pre-application (DCLG Guidance, 2015)
 helping the applicant identify and resolve issues at the earliest
stage
 enabling members of the public to influence proposed projects,
 helping local people understand the potential nature and local
impact of the proposed project
 enabling applicants to obtain important information about the
economic, social and environmental impacts of a scheme
 enabling potential mitigating measures to be considered and, if
appropriate, built into the project before an application is
submitted;
 identifying ways in which the project could, without significant
costs to promoters, support wider strategic or local objectives.
Brief overview of preapplication process requirements







notify the Secretary of State of the proposed application
identify whether the project requires an environmental impact
assessment
produce a Statement of Community Consultation and make this
available for inspection by the public
identify and consult statutory consultees
publicise the proposed application in accordance with regulations
and set a deadline for consultation responses of not less than 28
days
have regard to relevant responses to publicity and consultation
prepare a consultation report and submit it to the Secretary of
State.