Solar Powered Charging Station: Progress Report

Download Report

Transcript Solar Powered Charging Station: Progress Report

Solar Powered Charging
Station:
Mid-Term Presentation
Design Team:
Ben Hemp
Jahmai Turner
Rob Wolf, PE
Sponsors:
Conn Center for Renewable Energy
Dr. James Graham, PhD
Dr. Chris Foreman, PhD
Revision F, 10/23/11
1
Agenda
•
•
•
•
•
•
•
Project Objectives
Scooter Specifications
Scooter Charging Requirements
Trade Studies and Research
System Diagram
Major Components
Project Status
2
Project Objectives
• Design, fabricate, assemble and test a solar powered charging
station for a plug-in electric vehicle (EV)
• The electric vehicle to be used with the charging station will be a
pluggable electric motor scooter
• Tasks
• Optimize requirements
• Budgets
• Facilities
• Performance
•
•
•
•
Size and specify solar panels
Component research and evaluation
Component selection
Data collection and evaluation for the EV and charging station
3
Scooter Specifications
• Manufactured by NoGas LLC in
Nashville, TN
• 50 MPH top speed/50 mile
range
• 72 VDC, 40 AH Lithium batteries
with Battery Management
System (BMS)
• Regenerative braking
• Built-in charger
• 340 lb carrying capacity
• 120 VAC charging with 1 to 8 hr.
max charge time
• Front and rear hydraulic disk
brakes
• Hydraulic shocks front and rear
4
Scooter Charging Requirements
• Batteries: 72 VDC, 40 Amp-hour batteries
• Electrical Power = 2.9 kW
• So, the charging station should be able to supply
approximately 3.0 kWh to charge the batteries in one day
IF the batteries are fully discharged (3.0 kWh/day)
• The worst case day is the shortest day of the year, when
the sun is at its lowest angle
• Lowest efficiency due to solar angle, since the tilt of the solar
panels will be fixed
• A solar study is required to determine the range of
available energy
5
Solar Panels
• The Conn Center for Renewable Energy will furnish two solar
panels from their preferred vendor for this project
• However, we are tasked to design a fully-capable system, and
to implement a more limited capability this semester
• In order to understand the expandability of the system, the
design must accommodate the maximum requirement
• 3.0 kWh per day to charge the batteries if the bank is fully
discharged
• Worst case solar day
• The solar panels become the driving requirement for the
system design
• So, we must discuss them before proceeding further into the
presentation…
6
Solar Panel Overview
• PhotoVoltaic (PV) Solar Panels convert photons into electrical
power (DC voltage * current)
• The maximum efficiency for most commercial solar panels is
about 20%
• To create equivalent power, a lower efficiency solar panel
requires more surface area than a higher efficiency panel
• Efficiency is typically expressed in Watts/m2
• There are three major types of PV technology:
• Mono-crystalline, poly-crystalline, and thin-films
7
Solar Panel Types
Mono-crystalline
• Most efficient technology
• Most expensive $/watt
Poly-crystalline
• Mid-grade efficiency
• Less expensive than mono-crystalline per
equivalent $/watt
Thin-Film
• Least efficient technology
• Price in $/watt varies
• Available in thin flexible mats, artificial
shingles, and other form factors
8
Conn Center Solar Panels
Alternative Energies (Danville, KY)
• Received two 230W poly-crystalline panels
from the Conn Center
• Alternative Energies fabricates the panels
230 W Panel Specifications
• Each panel has 60 cells
• Vmax (1000W/m2, 25°C, AM 1.5) = 29.7 VDC
• Imax (1000W/m2, 25°C, AM 1.5) = 7.5A
• ~18% efficient
• Size = 39.375” (~3.25’) x 65.5” (~5.5’)
• ~ 2.0 yards2 or 1.9 m2
9
Solar Array DC Rating
• Each Conn Center panel to be provided is “DC Rated” at
230 Watts
• DC Rating means that AT THE EQUATOR, under normal
incidence of sunlight, on the brightest part of the day, the
selected panel will output 230 Watts
• When you move the panels to Zip Code 40208, performance
degrades rapidly
• Lower angle of incidence of the sun
• Many other variables
• In order to understand how many solar panels are required
to produce 3.0 kWh, a solar study is required….
10
Solar Study Results
• Used the NREL PVWATTS Grid Data Calculator for the solar
study
• http://www.nrel.gov/rredc/pvwatts/grid.html
• Uses hourly typical meteorological year weather data, and
• Allows users to create estimated performance data for any location
in the United States
• Provides a PV performance model to estimate annual energy
production
• Using the PVWATTS calculator, the following data was
entered:
• Zip code = 40208
• DC Rating = 1.5 kW, AC to DC Derate Factor = 0.77
• Solar Array Type = Fixed Tilt
• The results calculated are shown on the following slide….
11
PVWATTS Results
Worst Case
Month
12
Discussion of Solar Study Results
• The following observation can be obtained from the previous
slide, and the input data to the PVWATTS calculator
• For 1,500 Watts of DC Rated power, 6.5 solar panels of the type
provided by the Conn Center would be required
• For the worst case month (December), we would obtain 106 kWh
for the ENTIRE MONTH
• This equates to ~3.5 kWh/day
• So, a system that meets the charging requirement on the
worst month would require 7 panels
• We are being provided with 2 panels
• We need to design a system that will work with 2 panels, but
can be expanded to 7 panels
• Derating to a 2 panel design, we should be able to obtain
about 1.0 kWh/day
13
Inverter Definitions
Distributed vs. Centralized
• Distributed: Each solar panel is connected to its own inverter
• Centralized: Multiple solar panels are connected to one
inverter
Off-grid vs. Grid-tied
• Off-grid: Batteries are required for energy storage as a
secondary power source
• Grid-tied: Inverters are required to be tied to electrical grid as
a secondary power source
14
Inverter Tradeoffs
Microinverters
• Operate at lower DC voltages
(16-50VDC)
• Capable of working with low
quantities of solar panels
• Modular & expandable
• Lower initial cost
• Compensates for shading
(panels operate independently)
• Plug-and-Play cables
• Available remote interface
• Does not support batteries
Centralized Inverters
• Operate at higher DC voltages
(~150+ VDC)
• Must be procured at max power
required
• Not easily expanded
• Higher initial cost
• Lowest output panel can be weakest
link of system (series wiring)
• Standard wiring methods
• Typically requires more integration
for SCADA
15
Study Conclusions
• Use distributed inverters
• Allows expansion to the full system by adding inverters
as the system is expanded
• Grid tie the inverters
• Addresses the anti-islanding requirement
• Eliminate battery bank
• Required in project description
• Not feasible at this time, since commercial
inverters don’t support it
16
Block Diagram
17
Charging Station Components
•
•
•
•
•
•
Solar Panels
Inverter
Building Connection
Power Converter
Charging Station
Instrumentation
18
System Requirements
• Solar panels are customer furnished
• The inverter architecture has been previously derived from
research and trade studies
• The following slides describe the remaining design decisions
for the major components of the system
19
Solar Panels
20
Conn Center Solar Panels
Alternative Energies (Danville, KY)
• Received two 230W poly-crystalline panels
from the Conn Center
• Alternative Energies fabricates the panels
230 W Panel Specifications
• Each panel has 60 cells
• Vmax (1000W/m2, 25°C, AM 1.5) = 29.7 VDC
• Imax (1000W/m2, 25°C, AM 1.5) = 7.5A
• ~18% efficient
• Size = 39.375” (~3.25’) x 65.5” (~5.5’)
• ~ 2.0 yards2 or 1.9 m2
21
Inverters
22
Distributed Inverters
23
Enphase Features
•
•
•
•
•
•
•
•
One inverter per panel
Easy expandability
Improves shading performance
Pre-fabricated cables
15 year warranty
No single point system failure
Low voltage DC connections (22-40 VDC)
Includes optional gateway / monitoring
and analysis software
• Complies with UL1741/IEEE1547
24
Energy Storage
25
What to Do with Excess Power?
Grid-tied
Off-grid Using Batteries
• More efficient use of
power (ie – only limited
by building energy
consumption)
• Requires a branch circuit
• No additional space
required
• Unused solar energy
flows into building for
use
• Limited by Battery
capacity
• Only requires battery
charger for regulation
• Batteries need
conditioned room, which
will require additional
building penetration for
wiring
• Requires more
maintenance
26
Grid-tied System Safety Requirements
UL-1741 and IEEE-1547 Anti-Islanding standards
• Grid-tied system must comply with these two standards
• Anti-islanding: Inverter may not recognize loss of grid power if
load circuits operate at same frequency as grid (~60 Hz) causing it
to not shut off
• Standards ensure inverter detects loss of power grid to prevent
creating a live output (safety hazard to line workers) when grid
power is lost
27
Power Converter
28
Power Converter
• 240x480 – 120/240 V Transformer
• 2000 VA
29
Charging Station
30
Charging Station
• Provides 120 VAC Interface to Scooter
• NEMA 5-15R receptacle with weatherproof casing
• NoGas scooter features a three-prong charging cable
31
Instrumentation
32
Power Monitoring
• Solar energy generated is compared to the energy drawn from
the power grid for charging station
• Used to indicate whether the system is generating enough
energy for charging station
• Energy flowing from power grid means not enough solar
energy generation
• Smart meters with embedded web interface allow user to
connect from web browser at computer
33
Current Status
• Solar panels have been received
• Scooter has been purchased
• Eaton is donating transformer, disconnects, and power
monitoring equipment
• Grid circuit has been ordered from Physical Plant
34
Next Steps
•
•
•
•
•
Purchase all needed remaining equipment
Design solar panel mounting structure and equipment layout
Determine how all equipment will be connected
Work with electricians during installation
Test final product
35
Questions?
36