Transcript PPreview

Electrical PP1
•Basic features
•Electrical schematic
•Mechanical layout
•Prototyping
•Tests before production
•QC
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia
DAQ, DCS, Power Supply and Cables Review CERN, March 9 2004
Basic features:
• Accept Low Mass Tape on the module side and type II cable on the
power supply side.
• It provides pads for soldering of the low mass tapes to the printed
circuit.
• Two connectors are used for one type II cable to minimize the space
requirement
• It provides filtering of noise on the electrical lines
• Radiation hardness
• CO2 environment
• Forward and barrel have different mechanical constraints.
• 2.5 mm rule (IPC spec) for 500 V on opened areas obeyed (pins on
connectors will be pulled out)
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia
DAQ, DCS, Power Supply and Cables Review CERN, March 9 2004
Barrel schematic:
• control lines are AC coupled
to the shield
• Vcc , Vdd and HV lines are
AC coupled to their return
lines
•DGND is DC connected to
the shield
•AGND and HVGND are AC
connected to the shield
•ILEDa and ILEDb lines are
shorted
Forward schematic:
Same as PPB1 except:
•DGND is AC connected to
the shield
•ILEDb line on module side
and Temp2 line on PS side are
treated as a spare line
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia
DAQ, DCS, Power Supply and Cables Review CERN, March 9 2004
Barrel PPB1 has 8 conductor layers and accepts 6 modules
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia
DAQ, DCS, Power Supply and Cables Review CERN, March 9 2004
Forward PPF1 has 4 conductor layers and has 2 and 3 module versions.
On discs 1- 8
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia
DAQ, DCS, Power Supply and Cables Review CERN, March 9 2004
Forward PPF1 on disc 9:
There should be a drawing with just two modules
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia
DAQ, DCS, Power Supply and Cables Review CERN, March 9 2004
Prototyping:
•
•
•
•
Prototypes of PPB1 have been used in the system test before production,
noise performance of system was measured
Prototype harnesses have been assembled and tested with PPB1
Electrical prototypes of PPF1 have been used in the system test
Thermode soldering of tapes has been developed at RAL on protypes,
procedure improved with hot plate soldering at Taiwan during production
→ less cold solder joints
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia
DAQ, DCS, Power Supply and Cables Review CERN, March 9 2004
Tests before production
• Radiation hardness was checked up to 10 MRad (resistances,
capacitances measured) – no change of C and leakage currents was
measured
•
•
•
•
•
Accelerated aging at 100o C in CO2 was checked
Duration of aging: 72 hours (1st step) + 48 hours (2nd step)
Acceleration factor (20o → 100o) : 110 (Ea = 0.5 eV) , 8000 (Ea = 1.0
eV)
Interline resistance, HV leakage current and line + solder joint resistance
were measured before and after aging
Bias: 500 V at HV line during aging
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia
DAQ, DCS, Power Supply and Cables Review CERN, March 9 2004
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia
DAQ, DCS, Power Supply and Cables Review CERN, March 9 2004
QC during production:
After the assembly with components, the boards should be tested by the
producer. Following tests shall be performed:
1. Connectivity and Capacitance test
a.) Connection from the connector to the capacitance required
b.) Resistance up to 2 MΩ Between any two lines or ground - rejected
c.) Capacitance value agrees within 20 percent with nominal
2. Trace resistance test: measurement of the resistance between the
connector and LMT solder pad with 20 Ω range and 10mΩ resolution.
Resistance of each line should agree within 30 percent with the average
value (average measured for
that line within the production batch).
3.High voltage test: 500 V test for 10 s on the HV bias line. Leakage current
between HV bias line and HV return line and between HV bias line and
Ground shall be less than 100 nA.
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia
DAQ, DCS, Power Supply and Cables Review CERN, March 9 2004
Production:
• 440 (all) PPB1 have been already produced, B3 harnesses already mounted
• First batch of 620 PPF12 and 450 PPF13 in production, shipping to Taiwan
within two weeks
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia
DAQ, DCS, Power Supply and Cables Review CERN, March 9 2004
Related documents:
•
•
•
•
•
•
•
•
Explanation of LMT harness routing from PPF0 to PPF1 ATL-IS-EN-0026
PPB1 For Fibres and Low Mass Tapes ATL-IS-ES-0057.
SCT End-cap LM tape mapping table - module to PPF1 ATL-IS-EN-0024
End-cap Module and Services Position Numbering Scheme ATL-IS-EN0021
Spreadsheet of Low Mass Tape Length from PPF0 to PPF1 on SCT endcap ATLAS-IS-ES-0095
Technical specification for the manufacture and supply of low-mass tapes
for the ATLAS SCT detector ATL-IS-CS-0014
SCT Low-mass Power Tapes ATL-IS-AT-0013
PPF1, LMT and PP0 assemblies for the forward part of the SCT (in
preparation, draft on
http://wwwf9.ijs.si/%7Ecindro/cables/forward/ppf1assembliesEDMS.doc
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia
DAQ, DCS, Power Supply and Cables Review CERN, March 9 2004