Transcript Slide 1

33kV Superconducting Fault
Current Limiter
Dr. Chris Goodhand
Northern Powergrid
Adrian Wilson
Applied Superconductor
1
The Project
• Deployment of a 33kV superconducting fault current
limiter (SFCL)
• Builds on a previous project funded through IFI
•
•
•
•
Some results from this later
Device based on a relatively new class of materials
Collaboration between three DNOs
Device developer - Applied Superconductor Ltd, an SME
• Relatively large and long term project
Project Motivation
• The short and medium term future includes an increase in
the connection of low carbon technologies to our networks
• This will include increased distributed generation
connection at 33kV
• This can already be seen as an approaching trend – Wind,
anaerobic digestion, biomass
• There are barriers to this connection.
Project Motivation
• Increased fault level burden associated with these
connections
• Networks are run close to capacity, much switchgear and
protection is close to maximum fault level budget
• Additional prospective fault level contribution from
distributed generation limits our ability to connect
• Additional investment is therefore required to facilitate –
relatively slow and expensive process
Potential Solution
• Fault current limiting devices
• Superconducting Fault Current Limiters (SFCL)
• Advantages
• Large fault current clamping
• Disadvantages
• New devices, lots of potential but little track record
• Systems readiness issues
The Project
• Install and operate a 33kV Superconducting Fault Current
Limiter
• Deliver some key learning outcomes:
•
•
•
•
•
•
•
Where can these be applied?
How can they be operated?
How can they be integrated into our current systems?
What technical advantage do they confer?
Can we make a business case for their use?
Can we make a carbon case for their use?
What else can we discover through experiential learning with these
devices?
System Readiness Issues
Type Testing Specification
• Non-standard network component –
• Significant input from transformer and switchgear experts at
National Grid to identify which parts of their standards apply to the
Fault Current Limiter
• List of standards/tests for Type Testing now agreed
• Long process to get all technical stakeholders on board
7
System Readiness Issues
Design and planning
• Detailed design
complete
• Nomenclature
agreed
• Site Responsibility
Schedule updated
• Substation Control
System
• Protection scheme
agreed
L23
S18
S10
S14
L13
Brinsworth
(B371)
H23
H13
SGT2
SGT1
1R7
1T2
R2
2K0
SFCL
2K3
1R3
33kV
(T365)
33kV
(T364)
Other Systems Readiness Issues
• Currently a health and safety problem, unrelated to the
project, prevents access to the identified site
• Project too advanced to move to alternative location
• Eight month delay to installation and commissioning
• Supply Chain Problem
• Key supplier and intellectual property owner in administration
• ASL acquired IP and identified alternative component source
• Not critical path
9
Applied Superconductor Ltd.
Founded 2004 in Blyth, North East
England to commercialise Fault
Current Limiters
October 2009
First unit to be installed in UK
Summer 2012
Three units now installed
July 2012
Purchase parts of Zenergy Power
Applied Superconductor Globally
Applied Superconductor Ltd
Blyth
Applied Superconductor Inc
San Francisco
Applied Superconductor Pty
Woolongong
Fault Current Limiters
Inductive Limiters – Principles of Operation (HTS Magnets)
12
Fault Current Limiters
Inductive Limiters – Principles of Operation (HTS Magnets)
13
Fault Current Limiters
Inductive Limiters – Principles of Operation
The equivalent FCL inductance is a non-linear function of the instantaneous line current
FCL Inductance
I_Limited
is small at load current
X Coordinate
FCL Inductance
Increases dramatically
during a fault
Y Coordinate
L_cus
Equivalent Inductance
0.0060
+y
0.0050
CLR
Constant
Inductance
0.0040
0.0030
0.0020
0.0010
0.0000
-x
-0.0010
-15.0
+x
-y
-10.0
-5.0
0.0
5.0
Instantaneous AC Current [kA]
10.0
15.0
Fault Current Limiters
Inductive Limiters – Comparison to Reactors
50 %
Reactor
VOLTAGE
DROP
FCL
6.2%
2%
1.8%
0.5%
0.42 kA
100 MVA
1.3 kA
320 MVA
Current/Power
10 kA
Scunthorpe, Station Rd. – 11kV Installation
5 Lorry loads
Precision lifts
Clean Room Activities
Performance Under Fault – 11kV
• There was a three phase fault cable on a circuit out of
Station Road, Scunthorpe on 7th August 2012. The SFCL
had 3.3kA flowing through it on all 3 phases for 0.6s
• Device worked as expected under fault condition
• LV power lost, DC power maintained by batteries
• All systems recovered following the fault clearance
VOLTS ACROSS
CURRENT
VOLTS OUT
VOLTS IN
Performance Under Fault – 11kV
Key Learning – Dealing With The Unexpected
• Un-expected site access issue, despite attempted
mitigation, has resulted in project delay.
• Loss of key supplier and core intellectual property
• Difficult to foresee
• Exogenous Risks!
• Need a plan for when the unforeseen occurs.
Key Learning – Still Much To Learn
• Installation at Scunthorpe complex and resource
consuming
• 33kV project will address this learning
• Fault performance on 11kV device has been good
• System behaved as expected – good clamping
• Boosts confidence for the 33kV installaion
• 11kV Ancillary and support systems were impacted by
fault
• GPRS monitoring and warnings never received
• 33kV systems needs to be “hardened” against such problems
Project Outlook
•
•
•
•
Initial analyses and system design are complete.
Systems readiness issues overcome (?)
SFCL build in progress
Device installation and commissioning due summer 2013
after access issues resolved in Spring 2013
• Dissemination of learning expected, late 2012-2013