Preparation of the Hardware Commissioning
Download
Report
Transcript Preparation of the Hardware Commissioning
Hardware Commissioning
Status Report
Short Circuit Tests
Preparation for the first cool down
Enforce Safety
Quality Assurance
Tightening loose bolts
Resources
MAC, December 08,2006
Roberto Saban
The tests of the power converters in short circuit
18kV for the dipole circuits
400V for the others
UPS for all converters
above 4 kA
UA, UJ, RR
PC
DCCT
Water
Short Circuit
tunnel, UJ
Roberto Saban
MAC 061208
The power converters & the associated systems
952 / 968 already installed
Roberto Saban
MAC 061208
Preparation of the first cool down
Many non conformities on cabling
AC cables not crimped as per state of
the art
DC cables with extensions
Missing cable lengths
Late or just in time (but too just)
installation of equipment
(electronics, cables, etc)
Insufficient preparation of some
tests with respect to:
Co-activities
Access conditions
Safety conditions
It is the first one!
Roberto Saban
MAC 061208
High voltage tests of every circuit at warm
Ensure both insulation to ground and among circuits
Record reference values for leakage currents and
transfer functions
All the instrumentation electronics is not yet ready,
therefore it was decided to carry-out the tests
without it
all quench protection equipment disconnected from
DFB
all current lead heater cables disconnected from DFB
cryogenic instrumentation cables disconnected from
DFB
DC cables clamped to leads with insulation in between
1.9K
4.5K
Roberto Saban
MAC 061208
High voltage tests of every circuit at warm
Positioning of the DC water cooled cables on the DFB
4.5K
Roberto Saban
MAC 061208
High voltage tests of every circuit at warm
Safety measures & access restrictions
Roberto Saban
MAC 061208
Preparation of the first cool down
Ongoing individual system
tests
Orbit correctors
PC/cables polarity test
PC tests
HV tests
Installation of BLMs ongoing
Cryogenic operation
related activities
Purging & filling of the helium
vessel & lines. Flushing, next
week
Roberto Saban
MAC 061208
2007: the year of commissioning
Point 2
Roberto Saban
Point 4
Point 6
Point 8
MAC 061208
2007: the year of commissioning
short circuit tests
all sorts of system tests at warm
leak & pressure test
electrical quality assurance at warm
cool down from 300 to 80 K
Injection system MKI
TDI beam stopper
beam instrumentation
NC magnets
cool down from 80 to 4.5 K
cool down from 4.5 to 1.9 K
electrical quality assurance during
cool down
tuning of control loops
calibration of instrumentation
collimators
injection system control
injection system tests
electrical quality assurance at cold
individual system tests at cold
TI8 beam injection tests
powering tests
Roberto Saban
MAC 061208
2007: the year of commissioning
cool down from 300 to 80 K
cool down from 80 to 4.5 K
cool down from 4.5 to 1.9 K
electrical quality assurance during
cool down
tuning of control loops
calibration of instrumentation
electrical quality assurance at cold
individual system tests at cold
powering tests
450 Gev
lower fields
lower currents
Reduced commissioning
times for some of the
circuits
Roberto Saban
increased tolerance to temperature
variations
Reduced commissioning times for the
calibration of instrumentation and tuning
of temperature control loops
MAC 061208
Resources
Roberto Saban
MAC 061208
… in summary
Chasing all the completed warm
systems/components and organize
their commissioning
Short circuit tests (power converters,
cabling, infrastructure) more than
half completed
Preparing the cool down of the first
sector and … learning!
Very worried for the availability of
resources beyond the first two sectors
Roberto Saban
MAC 061208