Network Inventory Project

Download Report

Transcript Network Inventory Project

Network Inventory
Conceptual Framework
Tony Breach, Optical Network Manager
12. april 2017
Network Inventory - Index
Project Manager
Objective
Requirements
Supplier Inv. and Analysis
Decision making basis
Project Timeline
Project Manager
•
•
Project Manager: Heino Radmer
Project Team
•
•
•
•
Heino Radmer
Sören Westerberg
NU-NOC Member
Members that contribute to this project
•
•
Lars Bjørn
Mick Krag
BOL Objective
•
•
•
•
•
•
Base Objective
Topology – Physical/Logical
Hardware – Active/Passive
Connectivity – Fibers/Cables/Wireless
Sites
Software/Firmware Versions
End Objective
•
•
•
•
•
Device and physical network topology – including automatically
device topology discovery
Software and firmware package management
Real time End to End Logical topology including logical end user
connection representation
Device diagnostic log for tracking of degeneration in hardware
components
Network Resource Management
•
•
•
•
Device, card, port utilization for maintenance and network planning
End to end logical utilization
Dynamical interaction with the Service Assurance and Provisioning
engine
Simulation and planning tools
Circuit
Hardware
Aux
Proccesor
Fabric
Span
Card
Section
Fiber
Site
Requirements
•
BOL System
•
•
•
End System
•
•
•
TB – Web based GUI, Table and graphic presentation of Circuits
etc. Possible for open queries
Data Structure
•
•
Data container MYSQL
How to access and Query – Web based GUI
GUI, Query, Presentation
•
•
Data container will be Excel to MYSQL
How to access and Query – via Excel
Based on Heino’s Network Inventory Structure
Synchronisation of Data with Live Network
•
Automatic, Semi Automatic, Manual
Supplier Investigation and Analysis
•
Alcatel-Lucent
•
•
Workshop
Investigate the supplier market for NI’s
•
Look for co-operational NI’s to Service Assurance Systems
Decision Making Basis
•
•
•
•
•
•
•
•
Project Objective,
Project description
Benefits for NN
Price
Resources internal/external
Implementation
Timeline
Operation Responsibility
Timeline
•
•
•
•
•
•
•
•
•
•
Project start 01-03-2007
Vendor Workshop and presentations week 11
Decision Making Basis week 12
Installation Start Base System 01-05-2007
Project end Base System 01-07-2007
KPI’s
NN Transmission 100% ready date 01-07-2007
NN IP 75% ready date 01-07-2007
SUNET Transmission 80% ready date 01-07-2007
SUNET IP 50% ready date 01-07-2007