Transcript Not

New Build Projects & IT Networks
A Network Managers Perspective
Mark Clark
eAdvisor: Technology & Infrastructure, JISC RSC SW Scotland
New Build Projects & Networks
• The Team
–
–
–
–
–
–
Architect
Clerk of Works
H&S Officer
Project Manager
Project Sponsor
Technical Manager
New Build Projects & Networks
• Clerk of Works
–
–
–
–
–
Independent of contractors
Looks after College interest
Ensures standards of work
Supervises contractors on site
Attends & Informs project
management meetings
New Build Projects & Networks
• Project Manager
–
–
–
–
–
–
Independent
Manage documentation
Monitor milestones
Construction experience
Not a College manager
Not IT specialist
New Build Projects & Networks
• Project Owner
–
–
–
–
–
–
College SMT or Vice Principal
Overall budget control
Project management control
Overall Vision long term
Not day-to-day manager
Ensures build meets strategic
requirements
New Build Projects & Networks
• Technical Manager
– Specifies the network
– Thorough understanding of
technicalities
– Liaise with Clerk of Works
– Liaise with Project Manager
– Liaise with relevant contractors
– Daily Inspections of work done.
– Daily ‘chat’ with cable crew
supervisor
New Build Projects & Networks
• The Issues
–
–
–
–
–
–
–
–
–
–
–
Health & Safety
Network Design & Topology
Procurement Management
Active Components
Vertical Fibre
Horizontal UTP
Face Plates & Patch Panels
Server Room
Wiring Closet
Installation
Acceptance Criteria & Testing
New Build Projects & Networks
• Network Design & Topology
–
–
–
–
–
–
–
–
–
Architects Drawings
Server Rooms
Wiring Closets
Robust failover equipment
WiFi Access Point locations
IP Addressing Scheme
Security Policy ( Firewall config )
VLANS
Telephony over IP?
New Build Projects & Networks
• Procurement Management
–
–
–
–
–
Procurement Frameworks
European Journal
Request for Information (RFI)
Invitation To Tender (ITT)
Selection Criteria
•
•
•
•
Cost
Technical Suitability
Cost of Ownership
Future Proof
New Build Projects & Networks
• Active Components
–
–
–
–
–
–
Does it have to be Cisco?
Competitive vendors
Switch & Port density
VLAN propagation (802.3pQ)
Mixing existing switches with new
Training & Handover program
New Build Projects & Networks
• Vertical Fibre
–
–
–
–
–
Risers
Single Mode (mono mode)
Multi Mode
OTDR Testing
FCPC patch connectors ISP favourite
New Build Projects & Networks
• Horizontal UTP
–
–
–
–
–
–
–
Certification of installers
Warranty & TDR test results
LSZH
Containment, Trunking & Conduet
Cable tray above ceiling
Labelling of cables
Patch leads
New Build Projects & Networks
• Face Plates & Patch Panels
–
–
–
–
–
Numbering Scheme
Velcro wrap rather than cable ties
Cable management
“Moves & Changes” after installation
Cat 6 harnessing in panel?
New Build Projects & Networks
• Server & Comms Room
–
–
–
–
–
Overhead cable basket
Raised Floor
Air conditioning ( with UPS )
Fire suppression system
Cabinet accessibility
New Build Projects & Networks
• Wiring Closets
–
–
–
–
–
Resist cramming all into one location
Ventilation may be required
Cat 6 bend radius
Cable management (velcro wrap)
Don’t mix Cat 6 install with old Cat 5
patch cables
New Build Projects & Networks
• Installation
– Visit site regularly
– Health & Safety briefing
– Be diplomatic & manage
confrontation
– Don’t be a meddling dictator
– Change management
– Cat 6 bend radius etc
– Cable management
New Build Projects & Networks
• Acceptance Criteria & Testing
–
–
–
–
–
–
Cat 5 & 6 Cable certifying
Test sheets
Fibre optic ODTR tests
WiFi coverage survey
Routing Switching & VLAN tests
Agreed with vendor from the start
New Build Projects & Networks
• Conclusion
–
–
–
–
Download PDF document
Talk to your RSC ask for their input
Take ownership ASAP
Create new build RSC Forum and share
knowledge/experience
– Make sure your new campus has full JANET
service connectivity included in new build
budget (fibre etc)
WWW-RSC-SW-SCOTLAND.AC.UK
/Technical/Newbuild.htm
[email protected]
Mark Clark eAdvisor: Infrastructure