SCF Slides - BT Wholesale

Download Report

Transcript SCF Slides - BT Wholesale

.
Standard Contract Forum
3 November 2005
13.30
Customer Suite, BT Centre, London
www.btwholesale.com
Standard Contract Forum
Thursday 3 November 2005
AGENDA
1
Introduction and Notes of Previous Meeting
2
Consult 21
3
Lead Times
4
Review of New and Amended Schedules
5
Geographic VOIP Ranges
6
TMP Update
7
Any Other Business
www.btwholesale.com
Consult21
New Working Groups
The Groups
The People
The Objectives
28th October 2005
Nigel Scott
www.btwholesale.com
Consult21
4
Update Commentary
The scope and interactions of the WGs have been
modified based on feedback and internal Buddy “war
gaming”, in particular:
•The work of the Legacy Working Group is subsumed
into the appropriate Product Working Group
•A new “WG Management” group is formed
•The WG scopes have been fleshed out
WG Managemenet & Co-Chair Co-ordination
Consult21 Working Group Structure
Steering Board
To be a co-ordination
and escalation point
Communication
s
To keep end users
informed
Implementation &
Migration
To make tomorrow
happen
Commercial Group
Contract Group
Product Groups
Broadband
Line Access
Interconnect &
Portfolio
Point to Point
• Operational Planning
Architecture &
Framework Groups
• Implementation
Providing the underpinning
Systems & Processes
Network Structure,
Network Hooks
Top Level Themes
Architecture &
Framework
What do we
do with what
we've got
Legacy
Capability
timelines
Product Groups
21CN New
Implementation
& Migration
What (new) do we
want and when
Final say on delivering
products/services
Contract &
Commercial
How we do business
The Product WGs address both legacy transition and 21CN products
Consult21 Themes &
Contacts
Industry Co-Chair
Consult21
‘Buddy’
Key Player/s
Commercial Group
tba
Chris Evans
tba
Contract
tba
n/a
Keith Mitchinson
Claire Wallace
(Energis)
Andy Rudman
Joe Kelly
Chris Danzelman
(C&W)
Liz Walsh
Mike Cook
Gavin Young
(Bulldog)
Tom Saville
Communications
Implementation & Migration
Broadband
- LLU
Paul Barratt (O)
- Datastream / FAS
Bill Jones
- IPStream
Andy Jugg
Line Access
Justin Orde
(Spitfire)
Tom Saville
- WLR (legacy migration)
"Colin Reith" (O)
- MSAN Voice Access product(s)
Interconnect & Portfolio
Point to Point
- PCs & PPCs
- Ethernet (WES)
Mike Ward
Paul Griffin
(Energis)
Chris Evans
John Lee (Energis)
Tom Saville
Key Players & C0-Chairs to be re-confirmed
Mike Ward
Rob Thomas 8
Peter Newton (O)
Consult 21
Working Groups
Proposed Scopes
(Updated)
www.btwholesale.com
9
WG Management Group: Scope
Objective / Purpose
To own and manage the obligatory products
transformation plan (with clear understandings of what
constitutes no change, transfer engineering and equivalent
21CN products and where these will apply and impact
migration plans)
To manage the cross-WG Issues and Requirements
register(s) to facilitate the WGs to achieve their
objectives
To monitor and report on the critical delivery path for
the Plan, instigating appropriate actions to resolve
any problems.
To monitor the Consult21 process, proposing
Product Working Group Scopes
Broadband, Point to Point, Interconnect & Portfolio and Line Access
Objective / Purpose
To provide the detailed trajectory and critical path
plans for those products contained within the
obligatory products transformation plan, in particular
addressing withdrawal and transformation issues.
To agree the:
outline requirements / product descriptions for:
new products/services
transformation products e.g. VIECs
commercial and service wrap for the above
products
Architecture & Framework Scope
Systems & Processes, Network Hooks and Network Structure (e.g. MSAN) Working Groups
Objective / Purpose
To adopt interface standards, rules, functionality,
principles, frameworks etc that govern the
development and implementation of networks and
systems.
To ensure that as far as is practicable individual
product needs are catered for in a consistent way
with a minimum of re-invention
Application of standards, inherent resilience,
impairment standards, planning rules, firewalls etc
Scope
Implementation & Migration Scope
Objective / Purpose
To create an assured environment that enables the
migration of voice and non-voice products off affected
BT switches and platforms
To minimise any potential negative impact of
migration on end users
To capture learning from the migration processes for
application to BAU.
To introduce new products as defined by the Product
WGs.
Legacy vs New Products
Working Group
Legacy
21CN New
Interconnect & Portfolio
M
Broadband
M
C
C
Line Access
M
C
Point to Point
M
C
Point to Point includes all TDM and Ethernet type services
All Product Working Groups have both legacy & new product opportunities.
Many of the same people will be involved in Legacy & New discussions
Legacy work will conclude before New concludes, but they will overlap
Thank you
This is an evolving Consultation
Your feedback on the structure and
operation is very much appreciated
MIGRATION PROPOSAL:
CONSULTATION FRAMEWORK
Nigel Scott
This presentation provides an overview of the National Migration Proposal
and its associated Consultation
www.btwholesale.com
PRE- CONSULTATION FEEDBACK:
SUMMARY
8 responses were received
Feedback fell into 3 categories:
The data set
Additional information relating to DLE closure or clarifications has been incorporated
into the revised proposal
Clear methodology around document control included
Consultation Framework
Feedback received is consistent with Consultation Framework
Adjudication process defined for Consultation Phase only
Additional Information required to enable planning:
Voice Migration Methodology “Strawman” confirmed to facilitate Bi-lateral discussion
Development of a Roadmap identifying when additional information will be available
MIGRATION PROPOSAL & DATASET:
ISSUE 2
Audience:
Communications Providers with whom BT has direct interconnect or LLU
relationship
Objectives:
Provides details of the 21CN locations and high-level site-based details of how
the existing infrastructure will be mapped on to the 21CN infrastructure
enabling these Communications Providers to understand the implications for
their existing network infrastructure
To be viewed as a statement of BT’s current likely sequencing of migration
activity, subject to successful resolution of a series of complex commercial and
technical issues
Reflects regional workforce constraints in scheduling work
Smoother ramp up of migration activities to reflect training and realistic
productivity performance improvements
Outlines the consultation process which will operate from issue to 16 Dec 2005
Dataset disclosure:
Through NIPP or other appropriate closed user portal
Subset of locational information available through NISCC only
MIGRATION PROPOSAL:
CONSULTATION SCOPE
Aim is:
Production of a Plan of Record for business planning
purposes (Jan 06)
BT seeks views on the most appropriate and timely approach
to:
reach acceptable solution to all parties – recognising the schedule
will be fine tuned to reflect operational needs as migration
proceeds
effective change control management
minimising & anticipating the impact on customers
MIGRATION PROPOSAL:
CONSULTATION FRAMEWORK
& TIMETABLE
CONSULTATION (22/10 – 16/12)
(21/10 – 02/11)
•CP Impact Analysis
02/11-02/12
•Bi-laterals
•Interconnect CP’s
•Service Provider CP’s
•Multi-lateral consultation
through IMWG & expert
groups
05/12 – 16/12
• BT/Industry Board
reviews/agrees Migration
Proposal Change
Requests
• Expert Groups on
Migration methodology
• Communicate outcome
of Change Requests to
CP’s
• IMWG – 16/12/05
MIGRATION PROPOSAL:
BI-LATERAL TOPICS
Technical & Operations focus on three broad areas:
Implementation Considerations and Impacts
sequencing, timing, freeze periods, sensitive customer impacts
asset and operational optimisation, NGN business plan considerations
Migration Plan Change Requests
recording of Changes Required
recording of impacts & rationale
Migration Methodology
transfer engineering methodologies to be used to support Migration
minimising end user negative impact and operational resource optimisation
CONSULTATION PHASE:
CHANGE CONTROL & ADJUDICATION
Change Requests documented at Bi-laterals
Change Requests circulated to industry:
anonymous basis & excluding rationale
other CP’s identify impacts if such a change were to be accepted by BT
enables the acceptance or rejection to be done in light of impacts across
industry
BT Impact Analysis undertaken
W/C 12/12/05, BT and Industry convene a pre agreed Adjudication Board:
Accepts or rejects each Change Request
Membership is 3 from BT and 3 Industry nominees, under BT chairmanship
Chair has casting vote
STANDARD CONTRACTS FORUM
3 November 2005
Geoff Wills
Interconnect Links Lead Times
www.btwholesale.com
Standard Contract Forum
Thursday 3rd November 2005
Order
Original
timescale
New or proposed
timescale
Comments
Traffic route through
6 months
new point of connection
6 months
No Change
New traffic route
through an existing
POC
New traffic route
through an existing
POC with IEC
Route augmentation
65 days
45 days
New orders from
date to be briefed
75 days
65 days
Agreed at General
Contact Review
25 days
25 days
No change
Route augmentation
with IEC
35 days
25 days
Agreed at General
Contract Review
Standard Lead Time Reduction from 65 to 45
working days
Annex ‘A’
11.1.3
“New Traffic Routes between Switch Connections through an established Point of
Connection using the same technology, including the provision of new Traffic Routes by way of
additional Customer Sited Interconnect from a particular Operator site:”
11.1.5
“New Traffic Routes over IECs at a Switch Connection using the same technology:”
11.1.7
“Capacity Re-arrangements involving the provision of new Traffic Routes using the same
technology or a new technology already in service at the relevant Switch Connection:”
11.1.9
“Capacity Re-arrangements involving the provision of new Traffic Routes requiring IECs
using the same technology or a new technology already in service at the relevant Switch
Connection:”
.
Standard Contract Forum
Thursday 3 November 2005
Keith Mitchinson
3 November 05
www.btwholesale.com
Standard Contract Forum
Thursday 3 November 2005
REVISED SCHEDULE:
Schedule 143 – Carrier Pre – Selection
WITHDRAWN SCHEDULE:
Schedule 153/153A – Supply of Operator Branded
Telephone Directories
www.btwholesale.com
Standard Contract Review
Briefing on:
BT and Operator Geographic
NVS (New Voice Service Calls)
3rd November 2005
Les Stevens
Product Manager BT Core Network Services Interconnect
www.btwholesale.com
Contents
1. Product overview BT / Operator NVS Services
2. Ofcom Description summary
3. Current position Operator & BT NVS
4. BT Service update.
5. Applicable Contact Schedules – BT Proposal
6. Customer Feedback?
7. Next Steps?
Schematic Diagram of Operator NVS Geo Call Termination
Diagram below shows a typical application (may also be VOiP Originated?)
Customer
Originates a Call to
Operator Geo NVS
number.
TDM
Interconnect
BT TDM Network
Operator
PSTN
(TDM to IP
conversion)
IP ‘Cloud
Delivery of
IP Geo
NVS call
Schematic Diagram of BT Geo NVS Call Termination
Diagram below shows a typical application (May also be VOiP originated).
CP Customer
Originates a Call to
BT Geo NVS
number.
TDM
Interconnect
CP TDM Network
BT PSTN
(TDM to IP
conversion)
IP ‘Cloud’
Delivery of
IP Geo
NVS call
Ofcom Description - Extract from Ofcom statement of the 6/9/04
“Numbering Arrangements for New Voice Services”
Location Independent Electronic Communications Services (LIECS) Calls.
The Ofcom description of the characteristic of a Location Independent
Electronic Communications Services as defined in their statement of the
6/9/04 “Numbering Arrangements for New Voice Services” can be
summarised as follows:•The numbering plan of the Communications Provider offering the service
has no geographic significance.
•The location of the customers apparatus identified by a given telephone
number at the time of use is not permanently associated with a particular
network termination point.
•No revenue sharing with end users is allowed.
•Number translation to a geographic number is not involved and the
service is not a mobile service.
• Service does not have to offer PATS.
Current position Operator & BT NVS.
• Increase in Operator Geo code builds – believed to be NVS driven.
• BT Issued Interconnect Notification 05073 (12/08/05)
• BT Notification of opening on Geo ranges associated with NVS
(19/08/05).
• Draft Geo NVS schedule offered for discussion.
• Debate unfortunately deferred to Nov Meeting.
Update on BT Launch Of Geo NVS.
• Originally notified on 19th August.
• Original service ready date 4th October 2005.
• Some 10K allocations but mainly at Ofcom request sub allocations @ 1K.
• Problems encountered building @ 1K using automated systems.
• Manual build progressing.
• Upgrade to automated required – funding now agreed.
• New target completion by end April 2006.
• BT NVS Platform connected to 10 Trunk Switches (as per notification)
• Interconnection at these POI = Single Tandem rates.
• BT to issue revised timescale notice.
Contract Schedule for Geographic NVS ?
• Are Operators trading Geo NVS with BT under existing Geo Schedules?
• If so is this a sustainable position?
• Feedback to BT Proposed Schedule?
• Next steps to regularise this anomaly?
www.btwholesale.com
Standard Contract Forum
Briefing on:
Technical Master Plan
3rd November 2005
Kevin Young
BT Interconnect & Numbering Services
www.btwholesale.com
Contents
1. The Definition
2. BT’s view of the TMP content
3. TMP Information ownership & retention
The Definition
Contract (Annex D) Definition
Current:
“Technical Master Plan”
a document recording details of the Points
of Connection and the plans for development of further Points of
Connection;
Proposed:
“Technical Master Plan”
a document, retained and owned by both
Parties, recording details of the Points of Connection and the plans for
development of further Points of Connection;
BT’s view of the TMP content
There are three aspects of information that should be recorded within the
TMP, these are:
• The details of the interconnect between the Parties’ Systems and the
plans for future developments relating to interconnect. Typically, but not
solely, exchanged through the Capacity Profile/ACO process.
• The physical arrangements and Number Ranges, or part thereof, for
each of the Traffic Routes on an Interconnect Link. Information shall be
provided in accordance with the Provisioning Manual. Typically, but not
solely, exchanged through the Routing Plan process.
• The allocation of Interconnect Capacity to transmission capacity by
means of Tributary allocation charts as set out in the Provisioning
Manual.
The information relating to these three areas are, in the main, exchanged
within documentation set out within the Provisioning Manual.
TMP Information ownership & retention
The information that forms the TMP should be held by both BT and the CP
in order for both to manage the interconnection between the two networks.
Therefore, both BT and the CP are responsible for ownership and retention
of this information.
Whilst the information between BT and the CP is for the most part
exchanged within documentation set out within the Provisioning Manual, it
is for each to identify the means with which such information is recorded
within their own systems.
It is recognised by both BT and the CP that, from time to time, information
may be lost or its accuracy be questioned. Therefore, it is accepted by both
BT and the CP that requests for information exchange over and above the
normal flow may occur. These requests are on an occasional basis and the
scope is kept to a minimum in order to ensure that any such requests are
reasonable. In such circumstances both BT and the CP would generally
comply with requests of this nature.
AOB
3 November 2005
www.btwholesale.com