Power Protection

Download Report

Transcript Power Protection

™
Integrated Power, Cooling, and
Rack Infrastructure for
Critical Networks
Increase Availability While Decreasing Your
Total Cost of Ownership (TCO)
REV 5:
5/5/2003 3:38 PM
NCPI : Overview
Foundation for
“High Availability”
Networks
What drives data center costs?
• The concept of $/sqft is routinely used to describe
data center cost
• This suggests that area drives cost, which is false.
Per Watt
costs
75%
Power
Cooling
Service
Engineering
Per Sq Foot
costs
25%
Space
Improvements
Racks
Benefit of compaction is not present without
corresponding reduction in power
• $/Watt costs dominate TCO
• The concept of $/sqft suggests unrealistic TCO
improvements via compaction
Total Cost of Ownership
100%
80%
Reality: $$ are driven by Watts
60%
40%
If $$ were really driven by square feet
20%
0%
0
2
4
6
8
10
12
14
Compaction: KW Per Rack
16
18
20
Actual power draws in real data
centers
30%
>90% of
new data
centers
capability
% of Enclosures
25%
20%
Gartner
guidance
Max
1U
server
2002 actual data
ave = 1.5kW
Max
blade
server
15%
10%
5%
0%
0.5
1.5
2.5
3.5
4.5
5.5
6.5
7.5
8.5
9.5
10.5 11.5 12.5 13.5 14.5 15.5
Per Rack Power - kW
Powering high density racks
• Voltage, power, and connector requirements strongly
suggest the use of 3-phase power distribution to the
rack
• A 3-phase 20A power whip can provide 7.2kW per
whip, with both 120V and 208V available at the same
time
• Two or more of these whips can support extreme
density
Power and Cooling infrastructure limits the
area savings available from compaction
50
45
Area in sqft / kW
40
Total area of IT equipment and infrastructure
35
30
Area of power and cooling infrastructure
25
20
15
Area of IT equipment
10
5
0
1
2
3
4
5
6
7
8
9 10 11 12 13 14 15 16 17 18 19 20
Compaction density: KW Per Rack
Total area
does not
decrease
after about
5kW per rack
Conclusion
• It is challenging to cool isolated racks >6kW or groups
>4kW in conventional data centers
• Compaction without corresponding reduction in power
consumption is ineffective and expensive
• A practical approach to density is to establish density
limits
• 7.2 and 14.4 kW are natural per-rack density limit values
due to branch circuit limits
• Where ultra high density is required, fully ducted cooling
systems provide highest performance and predictability
More information on these subjects is available from APC
White Papers at www.apcc.com
Agility
Fact: Traditional approaches to increasing power and
cooling capacity can take up to a year or more to
implement, slowing business response to market.
“I need a
server.”
“I need more
capacity.”
2 Days
400 Days
“I have a
server.”
“I have more
capacity.”
The Speed of Business is the Speed of the IT Response!
Traditional Approach (400 day)
“I need more
capacity.”
Needs
Assessment
Custom Parts,
Applications
and Services
“I have more
capacity.”
Operation
Design Concept
Commissioning
Construction Design
Construction
What if……
• The Design Concept is built on standardized
parts that can be scaled to meet the need?
• Construction Design incorporates a “Lego
Block” approach of pre-engineered
components?
• Construction is mainly done in a factory
instead of on-site?
• Commissioning tests pre-integrated
infrastructure systems.
A Quick Review: The Next Generation
Data Center Design is…
• Modular
• Plug and Play
• Scalable
• Fault tolerant
• Portable
• Pre-engineered
• Module-based mistake-proof servicing
• Has Built-in management based on TCP IP standards
• Does not require raised floor
Solutions: System Level Challenges
• Live system can be expanded at will.
• Drastically reduces one-time engineering.
• Collapses the Design-Specify-Purchase-Commission Cycle.
• Standardized, off-the-shelf, cost effective components.
• No services or integration “surprises.”
• Much of the field installation replaced by pre-assembly.
• Standardized documentation and operations.and operation
Link to Movie
Scalable Data Center
Architecture for
Infrastructure On Demand™
Power for Closets and
Computer Rooms
UPS Options Summary
1 Rack:
Smart-UPS 1500
1 – 2 Racks:
1 – 4 Racks:
1 – 4 Racks:
1 – 10 Racks:
Smart-UPS 3000 (XL)
Smart-UPS 5000 (XL)
Symmetra RM 6kVA
Symmetra 12kVA
InfraStruXure Type A: 1-10
Data Center design
Type B
5 – 100 Racks
5 – 20 Racks:
frame
InfraStruXure 20kW
10 – 60 Racks:
frame
Symmetra PX 40kW
60 – 100 Racks:
frame
Symmetra PX 80kW
InfraStruXure 20kW Specifications
–
–
–
–
–
–
–
–
–
–
–
208V Nominal Input / Output (4-wire)
Double Conversion
Power factor corrected input
UP to 15 min Runtime (0.8 pf) with
internal batteries
20kVA/kW N+1
Up to 4 XR Battery Frames may be
connected for extended runtimes
Input voltage range: 166 – 240VAC
Input frequency range: 40 – 70 Hz
Efficiency: >91.5%
Overload capability
• 125% overload: continuous via
static bypass
• 150% for 30 seconds
• 1000% 500ms: via static bypass
Heat Dissipation = 6489 BTU/Hr
(1.9kW)
10-60 Racks: SYPX40
•
40kVA/40kW capacity in 10kVA/10kW power
module increments
– power factor corrected input
– fully rated inverter
•
Power modules arranged in N+1
configuration
•
Battery modules arranged in a parallel
redundant configuration
•
All modules are hot-swappable
•
Housed in a 35.5” NetShelter VX enclosure
– footprint = 5.67sq ft
– rolls through 7’ door
•
125% continuous rated, user replaceable
static switch
•
XR frames available for longer runtime
requirements
60-100 Racks: 80KW PDU w/Bypass
•
•
•
•
•
Housed in the VX Wide Enclosure
– just 36” deep, not 42”
Manual Maintenance Bypass
Capable of 208V, 480V, and 600V input
Contains a single 400A, (42) Position Panel
board
– CTO option to include up to (4) 80A subfeed breakers to rack mount Remote
Distribution Panels (RDP)
Additional CTO capabilities:
– Dual Feed (separate mains and bypass
feed – bypass feed must be 208V)
– Load Test Port connection
Symmetra PX Product Design Benefits
Power View
Redundant
Intelligence Module
Easy to read and navigate through menus
and functions
Acts as back-up for the Main
Intelligence Module
Power Module
Battery Module
Provides the flexibility to scale
power capacity and adds N+1
capability
Hot swappable for easy
replacement by trained user
Built-in Static Bypass Switch
Enables the UPS to transfer the load to
utility power, without interruption, in case
of heavy overload or faulty conditions
Symmetra PX
XR Battery Frame
– Same XR Frame as Symmetra PX 40kW
– Holds 8 battery modules
– A fully populated battery enclosure will provide
an ISX-20kW with 45 minutes of runtime (0.8pf)
– Weight: 2100 lbs fully loaded
– Up to 4 XR Enclosures can be added
InfraStruXure for Data Centers
TM
On-Demand Architecture for
Network-Critical Physical Infrastructure
Changing the way the world designs data centers…
InfraStruXure® Systems for Data
Center
Monitor Environmental
Conditions
Management Integration
Minimize implementation time by
quickly integrating your new design
into existing management system
Enhance the system with environmental
controls for earlier detection and faster
problem resolution
Scalable Cooling
Air removal solutions
(shown) and in-row cooling
solutions enhance scalability,
and allow for quick
deployment and adaptation
for IT upgrades
Rack Design
Vendor-neutral enclosure improves
adaptability for diverse IT environment
Available Options
Additional “add-on’s
available, including
ATS/Generator, Security,
Environmental, etc.
Present the Solution
Standby Power Generator
Automatic Transfer Switch
with Distribution Panel
Increase runtime requirements from
minutes to days
Delivers redundant power by
monitoring and controlling APC’s
Standby Power Generator and ATS
via the network
Integrated Power
and Cable
Distribution
Self contained power and
data cable distribution
eliminates the need for
raised floor
Integrated Cooling
Standard Components
Allows you to customize solution,
minimize human error, and lower
Mean-Time-To-Repair
Effectively capture the hot air
where it is created and deliver
cool air where it is required.
Symmetra PX Options and
Related Products
Environmental
Monitoring
External Battery
Enclosure
Rack-based, scalable
design for extended
runtimes
Identifies thermal
problems before damage
occurs
APC Global
Services
A variety of product
based and professional
services
PDU with System
Bypass
Configurable PDU in a
rack- based design
Remote
Monitoring
Monitoring and
performance trending of
enterprise power and
environmental infrastructure
Symmetra PX
The cooling dilemma
• 15kW of blade servers can be purchased today and
installed into a single rack.
• 11kW of 1U servers can be purchased today and
installed into a single rack
• People will attempt to install this equipment
(600W/sqft) in data centers where the industry
average load is 1.4kW per rack (45W/sqft).
Don’t forget about availability
• Redundancy of cooling becomes more complex and
harder to predict at higher density
• The Air Conditioning System must be on UPS after
approximately 120W / sq ft (4kW/rack) because the IT
system will overheat during the generator startup delay
• These are difficult technical problems which make it very
difficult to reliably cross the 150W/sq ft barrier
More Problems: Dynamic Power
Variation
•
Most IT equipment draws virtually constant power independent of its
computational load
•
Early 1U servers were based on desktop technology and exhibited power
that varied with function. This was the first significant exposure of the
data center to dynamic power variation
•
P4 Xeon and near term processors do not support power management.
•
Enlightened customers and possibly public policy will dictate that
processors manage power.
•
Consequence: The data center of the future will need improved
management tools to manage dynamic power variations without overload
or malfunction.
High density answers that do
work
• Careful hot-isle-cold-isle design
– Properly laid out racks
– Properly located returns over hot isles
– Eliminating raised floor bypass leakage
• Blanking panels
– Can reduce hotspot server intake air by up to 15
degrees F (see APC white paper #44)
• Limit: 3-4 kW per rack
Cooling capability limitations of
the raised floor
Raised floor power capability
7
Typical
Capability
Rack Power (KW)
6
With
Effort
Extreme
Impractical
5
4
3
2
1
0
0
100
200
300
400
500
600
Tile Airflow (CFM)
700
800
900
1000
Single tile per rack
10 degree C rise
Practical Limit: 3-4 kW per rack if one tile used
High density answers that do
work
• Hot air scavenging
systems
– Collect hot air at the
point of generation
– Route directly to
CRAC
– Snap-on retrofit
– Variable speed: as
needed
– Dual Path Power and
N+1
– Flexible, Movable
Wiring Closet Ventilation Unit
Airflow Diagram
Conditioned air
from outside the
room enters via
intake vent
Wiring Closet
Ventilation Unit
pulls warm air
from the room
Conditioned air
supplied to IT
equipment
Warm, exhaust air
Rises
Wiring Closet Ventilation Unit
Warm air is
exhausted from IT
equipment
InfraStruXure InRow SC Airflow
Heat rejected from
room to plenum
space
Condenser air
absorbs heat from
coil
Cool air from
plenum space pulled
into unit via fans
Hot exhaust air from
IT equipment pulled
into unit via fans
Heat transferred
to condenser coil
Evaporator coil
absorbs heat from air
Cool air is
supplied to row or
room
InfraStruXure InRow SC
InfraStruXure InRow RC
In-row air conditioning for medium to large data centers
including high density applications.
InfraStruXure InRow RC
Predictable cooling solution for an unpredictable environment
Rack Air Containment Airflow
Diagram
Rear
• Fans of InRow cooling
unit(s) distribute cool air
to front of IT equipment
• Air passes through
servers and absorbs
heat
• Server exhaust air is
prevented from escaping
by rear containment
• All exhaust air is
returned to InRow
cooling unit(s)
• Proper airflow through
the enclosure is ensured
Rack Air Removal Unit
Rear
Containment
NetShelter
SX Rack
InRow
Cooling
Unit
InRow
Cooling
Unit
Servers
Front
Containment
Front
Top Down View
InRow RC Applications
Up to 30 kW chilled water
• Hot Spots
– Server
consolidation
– Compaction
– Peak loads
 Capacity Planning
 Data center

expansion
Rightsizing
InfraStruXure InRow RC
 High Density
 Blade servers
 NAS storage devices
 1U servers
• Dynamic loads
– Batch
processing
– Grid
computing
InRow RC Product Design
Benefits
Dual A-B Power Inputs
Variable Speed Hot
Swappable Fans
Power redundancy and
protection
Rightsizes cooling
capacity, energy savings
Top or Bottom Piping
Connections
Cooling Coil
Removes heat using
chilled water
Air Filter
Flow Meter
Removes airborne particles,
protects coil
Measures water flow to
facilitate determining unit
kW output
Field Configurable
2-Way or 3-Way
Valve Operation
InfraStruXure InRow RC
Casters
Allows unit to move easily
Condensate Management
Detects and removes
condensation
TM
InfraStruXure
InRow RC Value Proposition
Predictable Cooling Solution for an
Unpredictable environment
Modular Solution that will adapt to the
changing IT world.
•Availability
–Predictable architecture
–Mean Time To Recover
•Agility:
– Standardized modules
– Capacity on demand
• TCO:
– Capacity per footprint
– Rightsizing
– Increase usable IT space
Changing the way the world designs data centers...
APC Solution Applied
VoIP and IP Telephony
InfraStruXure Solution for Data Centers
Agility
• Standardized Modules
– Raised Floor not required for cooling, reduces build
out and eliminates space constraints
– Short lead time
• Capacity on Demand
– Matches heat removal to the heat load
– Enabling variable capacity without raised floor
dependency (no requirement for constant pressure)
• High Density Capable
– Able to cool up to 60 kW in a single rack
InRow RC Summary
In-row air conditioning for medium to large data centers including high
density applications.
•
Modular design increases agility by providing scaleable solutions to add
cooling as demand increases.
•
Improved Energy Efficiency and Rightsizing reduces total cost of
ownership.
•
Placing the unit in the row of racks moves the source of cooling closer to
the heat load and minimizes air mixing thus improves availability.
•
Up to 30 kW Capacity
Predictable cooling solution for an unpredictable environment
InfraStruXure InRow RC
APC Management Solutions
Tools to remotely monitor and control, easily and economically.
 Network-Critical Physical
 UPS Management
Infrastructure
InfraStruXure Manager Appliance
 Environmental
UPS Network Management Cards
PowerChute Business Edition
Building Management Interface Card
Management Platform Integration
UPS enhancement cards
 Server Access
Management
Environmental Management System
Environmental Monitoring Unit
UPS Environmental Monitoring Card
Sensors
Management
Analog KVM Switches
Digital KVM Switches
Fliptop Monitor
Because when something changes, you need to know.
InfraStruXure Manager Applications
Appliance with licenses for 25, 100 or 1000 nodes.
Additional licenses available.
• Data Center
– Manage your
APC
InfraStruXure
– Manage other
APC devices
on the network
 Remote Branch Office
 Monitor remote
locations
 Give local personnel
read-only access
InfraStruXure Manager
 Network Closets
 Monitor locations
infrequently accessed
 Distributed
Network
 Monitor UPS &
other devices
dispersed
throughout the
network
Manageable Devices within the
InfraStruXure Management Architecture
Telnet
Use of Standards
Manage APC networked
devices via existing network
infrastructure.
HTTP (Web)
APC Network
Manageable
Device
ModBus*
InfraStruXure Manager
Email
* UPS and cooling products only
Fault Notifications
Email or SNMP notifications
ensures crucial situations are
dealt with in a timely manner.
SNMP
Integrating InfraStruXure Management into
Your Management Architecture
Building Management System
Integration
Building Power
Comfort Air
Manage critical building infrastructure from
single system via modbus
Enterprise Management
System Integration
Forward SNMP traps to your
preferred management system
Network
Manager
Network
Devices
Building Environment
Building
Management
System
Enterprise
Management
System
Manage NetworkCritical Physical
Infrastructure
Similar to server,
storage and networking
equipment.
Storage
Manager
Server
Manager
InfraStruXure
Manager
Cooling Devices
Storage
Devices
InfraStruXure Manager
Scalability
Rack Devices
Power Devices
Server Devices
Manage up to 1000
APC networked
devices
Network-Critical Physical
Infrastructure Management
 InfraStruXure Manager
Centralized management of your APC
network-critical physical infrastructure.
Appliance with 25, 100 or 1000 nodes.
Additional licenses available.
Management
InfraStruXure Management
Design Benefits
Network Management Card Screen Shot
Browser Accessible
Saves installing software on the
network management console.
Main Status Screen:
Overview of key
functions; UPS and card
Left-hand bar
Quick link other
functions