to get the file
Download
Report
Transcript to get the file
LARP CM15
Magnet Testing Working Group
SLAC, November 2nd 2010
Outline
Test requirements for the long HQ (consider two cases, 3.3 m coil
length - same as LQ - and 4 m coil length): possible facilities and
required upgrades.
Large diameter probes for field quality measurements: probe
fabrication, anti-cryostat/header modifications, possibility to perform
measurements in LHe
Magnet protection from shorts/ground faults
Electrical QA: status, analysis, etc.
Quench Detection
AOB
Test requirements for the long HQ: possible
facilities and required upgrades
Facilities (FNAL, BNL and CERN)
3.3-m long HQ coils
Fermilab:
No upgrades are required for testing from 4.5K to 2.5K.
Lambda plate is necessary for 1.9K test.
New warm bore is required for magnetic measurements
BNL:
PS
CERN: Test facility will be ready by March-April 2011
Cryostat working at 4.5-1.9 K range
20 kA power supply
Commissioning of DAQ and control systems
Test requirements for the long HQ: possible
facilities and required upgrades (cont’d)
4-m long HQ coils
BNL
CERN: Test facility will be ready by March-April 2011
Possible Upgrades
Fermilab:
“Lambda plate” for 30kA top plate
New warm finger with 90-mm outer and 70-mm inner diameter
(estimated cost ~ 20k$, 5-6 months from order placement)
BNL:
CERN:
Large diameter probes for field quality
measurements
What is a reference radius for magnetic measurements?
Define magnetic zone length
CERN asking for 95-mm of free bore diameter ?
Non-connection end, straight part, layer jump, connection end
Large diameter probes
Fermilab:
Currently using probes have a reference diameter of 46 mm
New PC board based probes with various reference radius
and length are fabricated (low cost).
Fabrication of new tangential coils will be much more
expensive and time consuming
BNL:
Large diameter probes for field quality
measurements (cont’d)
Large diameter probes
Anti-cryostat/Header modifications
CERN
Fermilab
Need new warm bore
Maximum outer/inner diameter is 90-mm/70-mm
Need to build new header, lambda plate and warm bore if
more than 90-mm reference diameter is required
Test in LHe
Magnet protection from shorts/ground faults
Fermilab
Symmetric coil (and heater) grounding
The maximum coil to ground voltage reduced by factor of 2
Ground current through the fault was significantly reduced (from
40 A to about 3 A)
Magnet protection from shorts/ground faults
(cont’d)
Fermilab:
Active coil ground fault detection
Isolated 5 V voltage source connected in series with the ground
resistor
Voltage drop develop across the
ground resistor (100-Ohm) in case
of coil to ground short
“Always armed”
Should not depend on power supply
voltage and magnet inductance
Is equally sensitive to ground fault at
different locations
Magnet protection from shorts/ground faults
(cont’d)
Fermilab
BNL:
Plan to implement an active heater ground fault system too
Ready to share experience
Plans for the ground fault detection
CERN:
Electrical QA: status, analysis, etc.
Pulse test
Initial and after test Hipots
.
Test procedure
Maximum voltage for the test
Fermilab performs Hipot at 1.9K too after first few quenches
Quench Detection
Fermilab
FPGA based quench management system was implemented in
addition to the existed VME based system
Difference of the Half-coil signals are mainly used for quench
detection
Current dependent thresholds implemented for the Half-coil
signal modules both in VME and FPGA based systems
Whole-coil signal also triggers quench
BNL
CERN
What else ?
Documentation:
Fermilab
Magnet description