Status_Septa_Activities_EYETS_2016-2017(28-02

Download Report

Transcript Status_Septa_Activities_EYETS_2016-2017(28-02

EYETS 2016-2017 septa status
Septa activities TE/ABT
Thierry Masson
28/02/2017
EYETS 2016-2017 Septa status
2
CPS General maintenance



Exchange of water filters (PS, PSB & Leir)
SEH 3M station maintenance done
Removal SMH42.3
done 8/02/2017
•
•
•
•

leak detected on SMH42.3 (removed from PS 8/2/2017)
SMH42.2 (2 years run) to be refurbishment asap
spare coil available (last one), ready to be chrome plated (external company)
new coil has to be ordered (EN/MME) ordered
SMH26



done
First new interlock control system installed (TE-ABT-EC)
Tests (Marco and Antoine)
done
done
Exchange of SEH23 done, under vacuum, HV connected
SMB to be re-installed after MU exchange


Exchange BESMH
Installation SMH42.1
28/02/2017
planned 6/03/2017
planned 14/03/2017
EYETS 2016-2017 Septa status
3
CPS General maintenance

LEIR extraction septum SMH40




Magnet removed from beam line for bake out (13-02-2017)
Refurbishment septa workshop (b.867) done
Silver coating of return conductor in TE/VSC lab ongoing
installation in Leir planned this week

Bake out septa wk.10 (PS), wk.12 (PSB), wk.11&12 (LEIR)
according to TE/VSC

Hardware tests (SEH & SMH)


PS planned 31-03
PSB to be planned (20-04 until 07-04)
28/02/2017
EYETS 2016-2017 Septa status
5
SPS General maintenance

MSE exchange in LSS4 (30-01-2017)
 MSE refurbished installed in LSS4 (14-02-2017)
 Vacuum leak test done

Bake out (200°C) water filters (x21) done
 Installation of water filter in LSS2 done
 ZS 3M station maintenance activities done
 ZS Anode/Cathode movement check (pot.
cleaning) done
28/02/2017
EYETS 2016-2017 Septa status
8
SPS General maintenance
To be done
 LSS2 3 oil containers (HV resistor) to be replaced ongoing
 Water filter in LSS4 planned next week
 Refill demineralized water from 13th March (EN-CV)
planned 13-03
 Testing girders movement, flow interlocks, WinCC
Need demineralized water
28/02/2017
EYETS 2016-2017 Septa status
9
Summary

EYETS progressing as planned, except:
•
SMH40, refurbishment of return conductors
started
Refurbishment of SMH42.2 started, ready by May.
28/02/2017
EYETS 2016-2017 Septa status